Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
05/03/2017
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LENN350816 T16-M0016
Contractors:
  • LENNAR ARIZONA CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM03485
Permit Status: Final
Permit Description: SFR LENN350816 T16-M0016
Start Date Submittal Complete Date Status  
05/03/2017 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 05/03/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM03485
Permit Status: Final
Permit Description: SFR LENN350816 T16-M0016
Total Outstanding Activity Conditions - 1
Date Name
05/03/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM03485
Permit Description: SFR LENN350816 T16-M0016
Total Completed Inspections - 30
Date Description Inspector Results Comments
05/18/2017 PLUMBING - ROUGH, SOIL NORTH Approved NO PRESSURE ON YARD LINE. OKAY TO COVER.
BRING HCS CO TO GRADE AND FINISH AT FINAL.
05/18/2017 PLUMBING - ROUGH, SOIL NORTH Approved
05/18/2017 PLUMBING - ROUGH, SOIL NORTH Approved
05/24/2017 PLUMBING - SEWER HCS CONNECT bbenedon Approved
05/24/2017 PLUMBING - YARD WTR LINE/TEST bbenedon Approved
05/24/2017 BUILDING PRE-SLAB bbenedon Approved
05/24/2017 EXCAVATION/LAYOUT REBAR & ZON bbenedon Approved
06/13/2017 ROOF NAILING bbenedon Approved
06/13/2017 EXT METAL CLIPS/EXT SHEATHING bbenedon Approved
06/13/2017 ELECTRIC - UNDERGROUND bbenedon Approved
06/13/2017 ELECTRIC - CABLE DROP bbenedon Approved
06/14/2017 ELECTRIC - CONSTRUCTION POWER BBENEDO1 Approved IVRS - Inspection :*
06/14/2017 TEP CLEARANCE - AM BBENEDON Approved ECO
07/13/2017 ELECTRIC - INTERMEDIATE bbenedon Approved
07/13/2017 PLUMBING - INTERMEDIATE bbenedon Approved
07/13/2017 PLUMBING - GAS PRESSURE TEST bbenedon Approved
07/13/2017 MECHANICAL - INTERMEDIATE bbenedon Approved
07/13/2017 U VALUE FOR WINDOW bbenedon Approved
07/13/2017 STUCCO MESH bbenedon Approved
07/13/2017 FRAMING bbenedon Approved
07/14/2017 ELECTRIC - UFER bbenedon Approved
07/27/2017 SHEET ROCK NAILING bbenedon Approved
09/11/2017 PLUMBING - PROGRESS BBENEDO1 Approved IVRS - Inspection :*
09/12/2017 GAS CLEARANCE BBENEDON Approved
10/24/2017 OUTDOOR LIGHTING FINAL BBENEDO1 Approved IVRS - Inspection :*
10/24/2017 MECHANICAL - FINAL BBENEDO1 Approved IVRS - Inspection :*
10/24/2017 PLUMBING - FINAL BBENEDO1 Approved IVRS - Inspection :*
10/24/2017 ELECTRIC - FINAL BBENEDO1 Approved IVRS - Inspection :*
10/24/2017 BUILDING - FINAL BBENEDO1 Approved IVRS - Inspection :*
10/26/2017 ENGINEERING - FINAL MRUSSO Approved