Permit: T17CM03479
Permit Details
Apply Date:
05/03/2017
Applicant:
ROBERT PALMOUR
Description:
NEW SFR
Permit Reviews
Permit Number - T17CM03479
Permit Status: Final
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/03/2017 | PLANS OK TO SUBMIT - RES | 06/06/2017 | COMPLETED |
| 06/06/2017 | RESIDENTIAL - BLDG/WWM | 06/30/2017 | COMPLETED |
| 06/30/2017 | RESUBMITTAL | 06/30/2017 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T17CM03479
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM03479
Permit Description: NEW SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2017 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
| 07/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 08/21/2017 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 08/21/2017 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
| 09/05/2017 | PLUMBING - SEWER HCS CONNECT | RGREENE | Approved | APPROVED AT THE STREET. ROUGH PLUMBING ENDS 10' FROM THE CURB. |
| 09/05/2017 | ELECTRIC - CONSTRUCTION POWER | RGREENE | Approved | APPROVED ECO |
| 09/06/2017 | TEP CLEARANCE - AM | ESTEVENS | Approved | ECO |
| 09/08/2017 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | STUCCO MESH | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/08/2017 | FRAMING | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/11/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED. FROM STREET TO HOUSE ROUGH SOIL CONNECTION |
| 09/12/2017 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 09/12/2017 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | APPROVED |
| 09/22/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | MECHANICAL - FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | PLUMBING - FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | OUTDOOR LIGHTING FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED |
| 11/08/2017 | BUILDING - FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/09/2017 | GAS CLEARANCE | ESTEVENS | Approved |