Permit: T17CM03476
Permit Details
Apply Date:
05/03/2017
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHO3090 T16-MOO36
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T17CM03476
Permit Status: Final
Permit Description: SFR DRHO3090 T16-MOO36
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/03/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 05/03/2017 | COMPLETED |
| 06/02/2017 | REVISION - - 1ST | 06/02/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03476
Permit Status: Final
Permit Description: SFR DRHO3090 T16-MOO36
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM03476
Permit Description: SFR DRHO3090 T16-MOO36
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2017 | PLUMBING - SEWER HCS CONNECT | MPUGH1 | Approved | IVRS - Inspection :* |
| 05/18/2017 | PLUMBING - ROUGH, SOIL | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | PLUMBING - YARD WTR LINE/TEST | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | ELECTRIC - CONSTRUCTION POWER | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | ELECTRIC - CABLE DROP | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | ELECTRIC - UNDERGROUND | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | BUILDING PRE-SLAB | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/02/2017 | TEP CLEARANCE - AM | MPUGH | Approved | TEC |
| 06/23/2017 | ELECTRIC - UFER | RGREENE1 | Approved | |
| 06/23/2017 | ELECTRIC - UFER | RGREENE1 | Approved | |
| 06/23/2017 | ROOF NAILING | RGREENE1 | Approved | |
| 07/11/2017 | EXT METAL CLIPS/EXT SHEATHING | mpugh1 | Approved | |
| 08/04/2017 | PLUMBING - GAS PRESSURE TEST | mpugh1 | Approved | |
| 08/04/2017 | FRAMING | mpugh1 | Approved | |
| 08/04/2017 | STUCCO MESH | mpugh1 | Approved | |
| 08/04/2017 | U VALUE FOR WINDOW | mpugh1 | Approved | |
| 08/04/2017 | ELECTRIC - INTERMEDIATE | mpugh1 | Approved | |
| 08/04/2017 | PLUMBING - INTERMEDIATE | mpugh1 | Approved | |
| 08/04/2017 | MECHANICAL - INTERMEDIATE | mpugh1 | Approved | |
| 08/18/2017 | SHEET ROCK NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
| 09/20/2017 | PLUMBING - PROGRESS | BBENEDO1 | Approved | IVRS - Inspection :* |
| 09/21/2017 | GAS CLEARANCE | BBENEDON | Approved | |
| 09/27/2017 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/27/2017 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/27/2017 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/27/2017 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/27/2017 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |