Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM03291
Permit Details
Apply Date:
04/27/2017
Applicant:
CATALANO, VINCENT VICTOR
Description:
PHYSICAL THERAPY
Architects:
- CATALANO, VINCENT VICTOR
Contractors:
- BAIRD BUILDERS INC ,
Permit Reviews
Permit Number - T17CM03291
Permit Status: C of o
Permit Description: PHYSICAL THERAPY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/27/2017 | COMMERCIAL - TI | 04/28/2017 | COMPLETED |
04/28/2017 | RESUBMITTAL | 08/18/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03291
Permit Status: C of o
Permit Description: PHYSICAL THERAPY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/27/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM03291
Permit Description: PHYSICAL THERAPY
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/22/2017 | ELECTRIC - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
09/20/2017 | PLUMBING - ROUGH, SOIL | MPUGH1 | Approved | IVRS - Inspection :* |
11/14/2017 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
11/14/2017 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
11/14/2017 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
11/21/2017 | SHEET ROCK NAILING | RGREENE1 | Approved | |
12/12/2017 | MECHANICAL - ABOVE CEILING | RGREENE1 | Approved | HARD LIDS ONLY. BRACE EXHAUST FANS ON THREE SIDES. |
12/12/2017 | PLUMBING - ABOVE CEILING | RGREENE1 | Approved | HARD LIDS |
12/12/2017 | ELECTRIC - ABOVE CEILING | RGREENE1 | Approved | HARD LIDS OKAY |
01/17/2018 | BUILDING ABOVE CEILING | BBENEDO1 | Approved | IVRS - Inspection :* |
01/24/2018 | ELECTRIC - CONSTRUCTION POWER | BBENEDO1 | Approved | IVRS - Inspection :* |
01/25/2018 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
02/08/2018 | MECHANICAL - FINAL | DQUINN | Approved | |
02/08/2018 | PLUMBING - PROGRESS | DQUINN | Approved | |
02/08/2018 | PLUMBING - FINAL | DQUINN | Approved | |
02/08/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
02/09/2018 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | |
02/09/2018 | BUILDING - FINAL | DQUINN | Approved | |
02/09/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
02/09/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
02/09/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved |