1601 W SAINT MARYS RD
Apply Date:
04/26/2017
Applicant:
CURTIS WALKER
Description:
HOSPITAL PHARMACY
Architects:
  • STERLING BARNETT LITTLE
Contractors:
  • LAYTON CONSTRUCTION COMPANY LLC

Permit Reviews

Permit Number - T17CM03267
Permit Status: L of c
Permit Description: HOSPITAL PHARMACY
Start Date Submittal Complete Date Status  
04/26/2017 PLANS OK TO SUBMIT - COMM 04/26/2017 COMPLETED Review Details
04/26/2017 COMMERCIAL - TI 06/06/2017 COMPLETED Review Details
07/19/2017 RESUBMITTAL 08/01/2017 COMPLETED Review Details
08/01/2017 RESUBMITTAL 09/15/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM03267
Permit Status: L of c
Permit Description: HOSPITAL PHARMACY
Total Outstanding Activity Conditions - 1
Date Name
04/26/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T17CM03267
Permit Description: HOSPITAL PHARMACY
Total Completed Inspections - 21
Date Description Inspector Results Comments
10/10/2017 PLUMBING - ROUGH, SOIL ESTEVEN1 Approved APPROVED
12/08/2017 ELECTRIC - INTERMEDIATE BSTEVENS Approved WIRING IN WALLS AND CEILING OK TO COVER.
12/08/2017 PLUMBING - INTERMEDIATE BSTEVENS Approved DWV AND WATER IN WALLS AND CEILING OK TO COVER.
12/08/2017 FRAMING BSTEVENS Approved PHASE 1-B ALL INTERMEDIATES OK IN WALLS
12/08/2017 MECHANICAL - INTERMEDIATE BSTEVENS Approved 3 CHASES IN WALLS OK TO COVER.
12/22/2017 SHEET ROCK NAILING BSTEVENS Approved PHARMACY 1-B ONLY
04/20/2018 ENGINEERING - FINAL MRUSSO Approved
06/28/2018 ELECTRIC - FINAL ESTEVEN1 Approved APPROVED
06/28/2018 ELECTRIC - ABOVE CEILING ESTEVEN1 Approved APPROVED
06/28/2018 BUILDING - PROGRESS ESTEVEN1 Approved APPROVED
06/28/2018 BUILDING ABOVE CEILING ESTEVEN1 Approved APPROVED
06/28/2018 PLUMBING - PROGRESS ESTEVEN1 Approved APPROVED
06/28/2018 PLUMBING - ABOVE CEILING ESTEVEN1 Approved APPROVED
07/02/2018 MECHANICAL - ABOVE CEILING ESTEVEN1 Approved APPROVED
07/03/2018 MECHANICAL - HYDRONIC PIPING ESTEVEN1 Approved APPROVED
07/05/2018 FIRE SPKLR - FINAL gsereno1 Approved Approved by CB
07/05/2018 FIRE - ALARM FINAL gsereno1 Approved
07/12/2018 BUILDING - FINAL RSHERRY Approved
07/12/2018 FIRE - FINAL gsereno1 Approved
07/12/2018 PLUMBING - FINAL RSHERRY Approved REVIEW OF THE WATER CHLORINATION REPORT COMPLETED
07/12/2018 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED