Permit: T17CM03080
Permit Details
Apply Date:
04/20/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SHELL BUILDING
Architects:
- GOLDSTEIN GENE
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T17CM03080
Permit Status: L of c
Permit Description: NEW SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/20/2017 | PLANS OK TO SUBMIT - COMM | 05/16/2017 | COMPLETED |
| 05/16/2017 | COMMERCIAL - NEW | 06/07/2017 | COMPLETED |
| 06/07/2017 | RESUBMITTAL | 06/09/2017 | COMPLETED |
| 06/09/2017 | RESUBMITTAL | 11/30/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03080
Permit Status: L of c
Permit Description: NEW SHELL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/20/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM03080
Permit Description: NEW SHELL BUILDING
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/07/2018 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/08/2018 | PLUMBING - BACK WATER VALVE | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/08/2018 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/23/2018 | BUILDING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/05/2018 | PLUMBING - YARD WTR LINE/TEST | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/14/2018 | STUCCO MESH | TVALENC1 | Approved | |
| 03/14/2018 | ROOF NAILING | TVALENC1 | Approved | IVRS - Inspection :* 1- ROOF NAILING IS OKAY FOR DRY IN. |
| 03/14/2018 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/20/2018 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/20/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/02/2018 | SHEET ROCK NAILING | DFLORES2 | Approved | |
| 04/11/2018 | ELECTRIC - TEMPORARY SERVICE | TVALENC1 | Approved | IVRS - Inspection :* CLEAR ELECTRIC ECO |
| 04/11/2018 | ELECTRIC - CONSTRUCTION POWER | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/12/2018 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 04/26/2018 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | |
| 04/26/2018 | ELECTRIC - UFER | TVALENC1 | Approved | |
| 04/26/2018 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | ELECTRIC - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | U VALUE FOR WINDOW | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 04/26/2018 | FIRE - FINAL | jvincent | Approved | shell only |
| 04/26/2018 | FIRE - ALARM FINAL | jvincent | Approved | no alarm |
| 04/26/2018 | FIRE SPKLR - FINAL | jvincent | Approved | no sprinks |
| 06/13/2018 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 06/13/2018 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | IVRS - Inspection :* |
| 06/13/2018 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 06/20/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 08/21/2018 | BUILDING - FINAL | COON | Approved | APPROVED BY Coon 08/20/2018 |