Permit: T17CM02892
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
874 E UNIVERSITY BL
Address NEW:
874 E UNIVERSITY BL
Apply Date:
04/14/2017
Applicant:
MEYER WILLIAM (CHUCK)
Description:
RESTAURANT & ADDITION
Architects:
- MEYER WILLIAM (CHUCK)
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T17CM02892
Permit Status: C of o
Permit Description: RESTAURANT & ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2018 | REVISION - - 3RD | 02/26/2018 | COMPLETED |
| 04/14/2017 | COMMERCIAL - TI | 04/14/2017 | COMPLETED |
| 04/14/2017 | COMMERCIAL - TI | 05/22/2017 | COMPLETED |
| 05/22/2017 | RESUBMITTAL | 05/24/2017 | COMPLETED |
| 05/26/2017 | REVISION - - 1ST | 05/26/2017 | COMPLETED |
| 08/21/2017 | REVISION - - 2ND | 10/06/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM02892
Permit Status: C of o
Permit Description: RESTAURANT & ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/14/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM02892
Permit Description: RESTAURANT & ADDITION
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/27/2017 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | |
| 08/09/2017 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | CMU WALLS TOPPED-OUT: RESTROOMS, JANITOR CLOSET, STAIRWELL. |
| 08/23/2017 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
| 08/25/2017 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
| 08/28/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | INCR |
| 09/13/2017 | FIRE SPKLR - UG, PIPING, HYDRO | jdonovan | Approved | |
| 09/29/2017 | FIRE SPKLR - UG PIPING FLUSH | jvincent | Approved | |
| 10/03/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | RESTROOMS AND MOP SINKS |
| 10/17/2017 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | MISSING HOSE BIB ON WEST SIDE |
| 10/17/2017 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | FRAMING | ESTEVEN1 | Approved | APPROVED |
| 10/17/2017 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
| 10/18/2017 | ELECTRIC - FINAL | ESTEVEN1 | Approved | |
| 10/20/2017 | BUILDING - FINAL | ESTEVEN1 | Approved | FOR TCO |
| 10/20/2017 | FIRE SPKLR - FINAL | jvincent | Approved | Still needs to add heads under upstairs overhang. |
| 10/23/2017 | ENGINEERING - FINAL | MRUSSO | Approved | 1) COMPLETE CONSTRUCTION 2) SITE NOT SAFE FOR OCCUPANCY |
| 10/27/2017 | ROOF NAILING | BSTEVENS | Approved | |
| 11/17/2017 | FIRE - FINAL | jvincent | Approved | Still needs to complete everything on previous list. Hood not interconnected to sprinkler monitoring. Will discuss this requirement with supervisor. Possibly not required. |
| 11/17/2017 | FIRE - ALARM FINAL | jvincent | Approved | |
| 11/21/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
| 11/22/2017 | GAS CLEARANCE | BSTEVENS | Approved | |
| 09/18/2018 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 10/16/2018 | BUILDING - PROGRESS | BSTEVENS | Approved | |
| 10/16/2018 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | |
| 10/16/2018 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
| 10/16/2018 | STUCCO MESH | BSTEVENS | Approved | |
| 10/16/2018 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
| 10/16/2018 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 10/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 10/17/2018 | OUTDOOR LIGHTING FINAL | bjones1 | Approved | Exterior lights in compliance |
| 10/17/2018 | MECHANICAL - FINAL | bjones1 | Approved | Radiant Heaters installed per listing Cooler installed in Basement, to service New Dining Room |
| 10/18/2018 | CERTIFICATE OF OCCUPANCY | BJONES1 | Approved | APPROVED PER 1090 BUILDIG FINAL |
| 10/18/2018 | HEALTH DEPT - FINAL 724-7908 | bjones1 | Approved | Approved by Jack Kincade RS 5-31-18 |