Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
04/13/2017
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT21S13 T13-M0005
Contractors:
  • RICHMOND AMERICAN CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM02876
Permit Status: Final
Permit Description: SFR RICHT21S13 T13-M0005
Start Date Submittal Complete Date Status  
04/13/2017 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 04/13/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM02876
Permit Status: Final
Permit Description: SFR RICHT21S13 T13-M0005
Total Outstanding Activity Conditions - 1
Date Name
04/13/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM02876
Permit Description: SFR RICHT21S13 T13-M0005
Total Completed Inspections - 26
Date Description Inspector Results Comments
04/25/2017 PLUMBING - SEWER HCS CONNECT NORTH Approved NO PRESSURE ON WATER LINE.
04/25/2017 PLUMBING - ROUGH, SOIL NORTH Approved
05/03/2017 BUILDING PRE-SLAB benedon Approved
05/03/2017 EXCAVATION/LAYOUT REBAR & ZON benedon Approved
05/25/2017 EXT METAL CLIPS/EXT SHEATHING bbenedon Approved
05/25/2017 ROOF NAILING bbenedon Approved
06/16/2017 PLUMBING - YARD WTR LINE/TEST benedon Approved
06/16/2017 ELECTRIC - UFER benedon Approved
06/16/2017 ELECTRIC - INTERMEDIATE benedon Approved
06/16/2017 ELECTRIC - CABLE DROP benedon Approved
06/16/2017 ELECTRIC - TEMPORARY SERVICE benedon Approved
06/16/2017 PLUMBING - GAS PRESSURE TEST benedon Approved
06/16/2017 MECHANICAL - INTERMEDIATE benedon Approved
06/16/2017 U VALUE FOR WINDOW benedon Approved
06/16/2017 STUCCO MESH benedon Approved
06/16/2017 FRAMING benedon Approved
06/19/2017 TEP CLEARANCE - AM BBENEDON Approved ECO
06/21/2017 PLUMBING - INTERMEDIATE benedon Approved
07/03/2017 SHEET ROCK NAILING bbenedon Approved
08/01/2017 PLUMBING - GAS PRESS TEST FNL BBENEDO1 Approved IVRS - Inspection :*
08/01/2017 OUTDOOR LIGHTING FINAL BBENEDO1 Approved IVRS - Inspection :*
08/02/2017 GAS CLEARANCE BBENEDON Approved
08/04/2017 MECHANICAL - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/04/2017 PLUMBING - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/04/2017 ELECTRIC - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/04/2017 BUILDING - FINAL BBENEDO1 Approved IVRS - Inspection :*

Documents

File Name Document Type  
None DOCUMENTS VIEW