Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
04/13/2017
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRH3055 T16-MOO59
Contractors:
  • D R H TUCSON CONSTRUCTION

Permit Reviews

Permit Number - T17CM02870
Permit Status: Final
Permit Description: SFR DRH3055 T16-MOO59
Start Date Submittal Complete Date Status  
04/13/2017 RESIDENTIAL - BLDG/ZONING-WALKTHRU 04/14/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM02870
Permit Status: Final
Permit Description: SFR DRH3055 T16-MOO59
Total Outstanding Activity Conditions - 1
Date Name
04/13/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM02870
Permit Description: SFR DRH3055 T16-MOO59
Total Completed Inspections - 25
Date Description Inspector Results Comments
04/20/2017 ELECTRIC - UNDERGROUND bbenedon Approved
04/20/2017 ELECTRIC - CONSTRUCTION POWER bbenedon Approved
04/21/2017 OUTDOOR LIGHTING FINAL BBENEDON Approved ECO
04/26/2017 PLUMBING - SEWER HCS CONNECT NORTH Approved
04/26/2017 PLUMBING - YARD WTR LINE/TEST NORTH Approved
04/26/2017 PLUMBING - ROUGH, SOIL NORTH Approved
05/04/2017 BUILDING PRE-SLAB benedon Approved
05/04/2017 ELECTRIC - CABLE DROP benedon Approved
05/05/2017 TEP CLEARANCE - AM BBENEDON Approved ECO
05/24/2017 ROOF NAILING BBENEDO1 Approved IVRS - Inspection :*
05/24/2017 EXT METAL CLIPS/EXT SHEATHING BBENEDO1 Approved IVRS - Inspection :*
06/16/2017 U VALUE FOR WINDOW NORTH Approved
06/16/2017 STUCCO MESH NORTH Approved
06/19/2017 MECHANICAL - INTERMEDIATE NORTH Approved
06/19/2017 PLUMBING - INTERMEDIATE NORTH Approved
06/19/2017 ELECTRIC - INTERMEDIATE NORTH Approved
06/19/2017 FRAMING NORTH Approved
06/19/2017 EXCAVATION/LAYOUT REBAR & ZON NORTH Approved
06/28/2017 SHEET ROCK NAILING bbenedon Approved
08/22/2017 ELECTRIC - UFER BBENEDO1 Approved IVRS - Inspection :*
08/22/2017 PLUMBING - PROGRESS BBENEDO1 Approved IVRS - Inspection :*
08/22/2017 MECHANICAL - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/22/2017 PLUMBING - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/22/2017 ELECTRIC - FINAL BBENEDO1 Approved IVRS - Inspection :*
08/22/2017 BUILDING - FINAL BBENEDO1 Approved IVRS - Inspection :*