Permit: T17CM02325
Permit Details
Apply Date:
03/24/2017
Applicant:
STEVE CRADY, GRESHAM SMITH AND PARTNERS
Description:
NEW VISITOR CENTER
Contractors:
- BRASFIELD AND GORRIE L L C ,
Permit Reviews
Permit Number - T17CM02325
Permit Status: C of o
Permit Description: NEW VISITOR CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/24/2017 | PLANS OK TO SUBMIT - COMM | 03/24/2017 | COMPLETED |
03/24/2017 | COMMERCIAL - NEW | 05/22/2017 | COMPLETED |
05/22/2017 | RESUBMITTAL | 06/08/2017 | COMPLETED |
06/08/2017 | RESUBMITTAL | 08/03/2017 | COMPLETED |
08/08/2017 | REVISION - - 1ST | 08/18/2017 | COMPLETED |
08/23/2017 | REVISION - - 1ST | 09/07/2017 | COMPLETED |
09/07/2017 | REVISION - - 1ST | 10/12/2017 | COMPLETED |
11/13/2017 | REVISION - - 2ND | 11/16/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM02325
Permit Status: C of o
Permit Description: NEW VISITOR CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/24/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM02325
Permit Description: NEW VISITOR CENTER
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2017 | ELECTRIC - UFER | RCAMACHO | Approved | |
10/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
11/14/2017 | BUILDING - PROGRESS | RCAMACHO | Approved | 4' MASONRY LIFT THROUGHOUT |
11/14/2017 | BUILDING - PROGRESS | mramber1 | Approved | stemwall ok |
11/15/2017 | ELECTRIC - PROGRESS | RCAMACHO | Approved | FLOOR BOX TEAM ROOM CONDUIT UNDER 18' BURIAL AT EXTERIOR ENCASED IN CONCRETE |
11/15/2017 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | |
11/16/2017 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | FOOTPRINT OF BUILDING ONLY |
12/13/2017 | SITE - SEWER | RCAMACHO | Approved | EXCEPT HCS CONNECTION |
12/15/2017 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
12/15/2017 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
12/15/2017 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | TOP OUT MULTI PURPOSE TOP OUT CONFERENCE ROOM ONLY |
12/18/2017 | PLUMBING - YARD WTR LINE/TEST | RCAMACH1 | Approved | EXCEPT AT METER |
01/23/2018 | ROOF NAILING | rbaldwin | Approved | |
01/23/2018 | MECHANICAL - INTERMEDIATE | rbaldwin | Approved | |
01/23/2018 | PLUMBING - INTERMEDIATE | rbaldwin | Approved | |
01/23/2018 | PLUMBING - PRE SLAB | rbaldwin | Approved | |
02/02/2018 | EXT METAL CLIPS/EXT SHEATHING | rbaldwin | Approved | |
03/12/2018 | MECHANICAL - PROGRESS | rbaldwin | Approved | |
03/12/2018 | MECHANICAL - ABOVE CEILING | rbaldwin | Approved | |
03/12/2018 | PLUMBING - PROGRESS | rbaldwin | Approved | |
03/12/2018 | PLUMBING - ABOVE CEILING | rbaldwin | Approved | |
03/12/2018 | ELECTRIC - ABOVE CEILING | rbaldwin | Approved | |
03/12/2018 | ELECTRIC - INTERMEDIATE | rbaldwin | Approved | |
03/12/2018 | SHEET ROCK NAILING | rbaldwin | Approved | |
03/12/2018 | BUILDING ABOVE CEILING | rbaldwin | Approved | |
03/12/2018 | FRAMING | rbaldwin | Approved | |
03/16/2018 | ELECTRIC - CONSTRUCTION POWER | rbaldwin | Approved | |
03/19/2018 | TEP CLEARANCE - AM | RBALDWIN | Approved | ECO |
04/16/2018 | ELECTRIC - FINAL | RBALDWIN | Approved | |
04/16/2018 | U VALUE FOR WINDOW | RBALDWIN | Approved | |
04/26/2018 | PLUMBING - ROUGH, SOIL | RBALDWIN | Approved | |
04/27/2018 | MECHANICAL - FINAL | RBALDWIN | Approved | |
05/01/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
05/01/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
05/02/2018 | ELECTRIC - SERVICE UPGRADE | RBALDWIN | Approved | |
05/02/2018 | PLUMBING - GAS PRESS TEST FNL | RBALDWIN | Approved | |
05/03/2018 | PLUMBING - FINAL | RBALDWIN | Approved | |
05/03/2018 | BUILDING - FINAL | RBALDWIN | Approved | |
05/03/2018 | FIRE SPKLR - FINAL | RBALDWIN | Approved | |
05/04/2018 | RIGHT OF WAY - FINAL | ENEWCOMB | Approved | |
05/04/2018 | NPPO - FINAL | MRUSSO | Approved | |
05/04/2018 | SIGN - FINAL | MRUSSO | Approved | |
05/04/2018 | LANDSCAPE - FINAL | MRUSSO | Approved | |
05/04/2018 | ENGINEERING - FINAL | MRUSSO | Approved |