Permit: T17CM01721
Permit Details
Apply Date:
03/03/2017
Applicant:
LAND DEVELOPMENT CONSULTANTS LLC
Description:
RESTAURANT
Architects:
- WINDLE, DAVID SCOTT
Contractors:
- MC MANUS CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM01721
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/03/2017 | PLANS OK TO SUBMIT - COMM | 03/03/2017 | COMPLETED |
03/03/2017 | COMMERCIAL - NEW | 04/03/2017 | COMPLETED |
04/20/2017 | RESUBMITTAL | 06/06/2017 | COMPLETED |
06/06/2017 | RESUBMITTAL - TI ALL | 06/29/2017 | COMPLETED |
06/29/2017 | RESUBMITTAL | 06/29/2017 | COMPLETED |
06/29/2017 | RESUBMITTAL | 07/28/2017 | COMPLETED |
07/28/2017 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/28/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01721
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM01721
Permit Description: RESTAURANT
Total Completed Inspections - 42
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/28/2017 | ELECTRIC - UFER | AQUIROZ | Approved | |
07/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | |
08/01/2017 | PLUMBING - YARD WTR LINE/TEST | mramber1 | Approved | |
08/23/2017 | PLUMBING - BACK WATER VALVE | mramber1 | Approved | |
08/24/2017 | PLUMBING - SEWER HCS CONNECT | mramber1 | Approved | |
08/24/2017 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | |
08/30/2017 | STEM WALL/RETAINING WALL | mramber1 | Approved | |
09/06/2017 | EXT METAL CLIPS/EXT SHEATHING | mramber1 | Approved | |
09/12/2017 | ROOF NAILING | mramber1 | Approved | |
09/20/2017 | ELECTRIC - PROGRESS | mramber1 | Approved | secondaries from transformer to bldg ok |
09/20/2017 | STUCCO MESH | mramber1 | Approved | |
09/21/2017 | FRAMING | mramber1 | Approved | |
09/21/2017 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
09/26/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
09/26/2017 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
09/26/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
09/26/2017 | PLUMBING - PROGRESS | mramber1 | Approved | |
09/29/2017 | SHEET ROCK NAILING | mramber1 | Approved | |
10/05/2017 | REINFORCED MASONRY PRE-GROUT | mramber1 | Approved | |
10/12/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
10/20/2017 | GAS CLEARANCE | MRAMBER | Approved | |
10/20/2017 | BUILDING ABOVE CEILING | mramber1 | Approved | |
10/20/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
10/23/2017 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
10/23/2017 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
10/26/2017 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
10/27/2017 | FIRE - FINAL | jvincent | Approved | two outstanding items. assembly permit was obtained today. co2 permit in the works. they are getting bids. |
10/30/2017 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | |
10/31/2017 | U VALUE FOR WINDOW | DQUINN | Approved | |
10/31/2017 | BUILDING - PROGRESS | DQUINN | Approved | |
10/31/2017 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
10/31/2017 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
10/31/2017 | MECHANICAL - HOODS | DQUINN | Approved | |
10/31/2017 | PLUMBING - ROOF DRAINS | DQUINN | Approved | |
10/31/2017 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
10/31/2017 | BUILDING PRE-SLAB | DQUINN | Approved | |
10/31/2017 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
10/31/2017 | MECHANICAL - FINAL | DQUINN | Approved | |
10/31/2017 | PLUMBING - FINAL | DQUINN | Approved | |
10/31/2017 | ELECTRIC - FINAL | DQUINN | Approved | |
10/31/2017 | BUILDING - FINAL | DQUINN | Approved | |
11/03/2017 | ENGINEERING - FINAL | RLEDONNE | Approved |