Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
03/01/2017
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LENN3570 T16-M0052
Contractors:
  • LENNAR ARIZONA CONSTRUCTION INC

Permit Reviews

Permit Number - T17CM01641
Permit Status: Final
Permit Description: SFR LENN3570 T16-M0052
Start Date Submittal Complete Date Status  
03/01/2017 RESIDENTIAL - BLDG/ZONING-WALKTHRU 03/07/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM01641
Permit Status: Final
Permit Description: SFR LENN3570 T16-M0052
Total Outstanding Activity Conditions - 1
Date Name
03/01/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM01641
Permit Description: SFR LENN3570 T16-M0052
Total Completed Inspections - 28
Date Description Inspector Results Comments
03/16/2017 PLUMBING - ROUGH, SOIL bbenedon Approved
03/16/2017 PLUMBING - YARD WTR LINE/TEST bbenedon Approved
03/16/2017 PLUMBING - SEWER HCS CONNECT bbenedon Approved
03/24/2017 BUILDING PRE-SLAB bbenedon Approved
03/24/2017 EXCAVATION/LAYOUT REBAR & ZON bbenedon Approved
04/10/2017 ROOF NAILING bbenedon Approved
04/10/2017 EXT METAL CLIPS/EXT SHEATHING bbenedon Approved
04/17/2017 TEP CLEARANCE - AM DQUINN Approved ECO
04/17/2017 ELECTRIC - CONSTRUCTION POWER dquinn Approved
04/17/2017 ELECTRIC - CABLE DROP dquinn Approved
05/08/2017 STUCCO MESH BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 U VALUE FOR WINDOW BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 MECHANICAL - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 PLUMBING - GAS PRESSURE TEST BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 PLUMBING - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 ELECTRIC - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
05/08/2017 FRAMING BBENEDO1 Approved IVRS - Inspection :*
05/18/2017 SHEET ROCK NAILING NORTH Approved
07/06/2017 PLUMBING - PROGRESS bbenedon Approved gas
07/07/2017 GAS CLEARANCE BENEDON Approved
07/17/2017 ENGINEERING - FINAL DROBERTS Approved
07/17/2017 BUILDING - FINAL bbenedon Approved
07/17/2017 ELECTRIC - UFER bbenedon Approved
07/17/2017 ELECTRIC - UNDERGROUND bbenedon Approved
07/17/2017 PLUMBING - FINAL bbenedon Approved
07/17/2017 MECHANICAL - FINAL bbenedon Approved
10/08/2019 OUTDOOR LIGHTING FINAL DMERANZ1 Approved APPROVED PER 1090 APPROVAL
10/08/2019 ELECTRIC - FINAL DMERANZ1 Approved APPROVED PER 1090 APPROVAL

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW