Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM01456
Permit Details
Apply Date:
02/22/2017
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRH3070 T16-MOO61
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T17CM01456
Permit Status: Final
Permit Description: SFR DRH3070 T16-MOO61
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/22/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 02/22/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01456
Permit Status: Final
Permit Description: SFR DRH3070 T16-MOO61
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/22/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM01456
Permit Description: SFR DRH3070 T16-MOO61
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2017 | PLUMBING - ROUGH, SOIL | bbenedon | Approved | |
| 03/14/2017 | PLUMBING - YARD WTR LINE/TEST | bbenedon | Approved | |
| 03/14/2017 | PLUMBING - SEWER HCS CONNECT | bbenedon | Approved | |
| 03/23/2017 | ELECTRIC - UNDERGROUND | bbenedon | Approved | |
| 03/23/2017 | ELECTRIC - CONSTRUCTION POWER | bbenedon | Approved | |
| 03/23/2017 | ELECTRIC - UFER | bbenedon | Approved | |
| 03/23/2017 | BUILDING PRE-SLAB | bbenedon | Approved | |
| 03/23/2017 | EXCAVATION/LAYOUT REBAR & ZON | bbenedon | Approved | |
| 04/14/2017 | ROOF NAILING | JJaworsky | Approved | |
| 04/14/2017 | EXT METAL CLIPS/EXT SHEATHING | JJaworsky | Approved | |
| 05/05/2017 | STUCCO MESH | bbenedon | Approved | |
| 05/05/2017 | U VALUE FOR WINDOW | bbenedon | Approved | |
| 05/05/2017 | ELECTRIC - INTERMEDIATE | bbenedon | Approved | |
| 05/05/2017 | PLUMBING - PROGRESS | bbenedon | Approved | |
| 05/05/2017 | MECHANICAL - INTERMEDIATE | bbenedon | Approved | |
| 05/08/2017 | PLUMBING - INTERMEDIATE | NORTH | Approved | |
| 05/08/2017 | FRAMING | NORTH | Approved | |
| 05/17/2017 | SHEET ROCK NAILING | JJaworsky | Approved | |
| 06/14/2017 | ELECTRIC - CABLE DROP | bbenedon | Approved | |
| 06/15/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 06/27/2017 | BUILDING - FINAL | bbenedon | Approved | |
| 06/27/2017 | ELECTRIC - FINAL | bbenedon | Approved | |
| 06/27/2017 | OUTDOOR LIGHTING FINAL | bbenedon | Approved | |
| 06/27/2017 | PLUMBING - FINAL | bbenedon | Approved | |
| 06/27/2017 | MECHANICAL - FINAL | bbenedon | Approved |