Permit: T17CM00837
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
3241 N MOUNTAIN AV
Address NEW:
3241 N MOUNTAIN AV
Apply Date:
02/01/2017
Applicant:
A MANZANA HOMES LLC
Description:
UPGRADE TO 200AMPS/ REMODEL MASTER BEDROOM/ DETACHED GARAGE ADDITION
Contractors:
- A MANZANA HOMES LLC
Permit Reviews
Permit Number - T17CM00837
Permit Status: Final
Permit Description: UPGRADE TO 200AMPS/ REMODEL MASTER BEDROOM/ DETACHED GARAGE ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/01/2017 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 02/02/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM00837
Permit Status: Final
Permit Description: UPGRADE TO 200AMPS/ REMODEL MASTER BEDROOM/ DETACHED GARAGE ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/01/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM00837
Permit Description: UPGRADE TO 200AMPS/ REMODEL MASTER BEDROOM/ DETACHED GARAGE ADDITION
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/25/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 05/16/2017 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 05/16/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 06/29/2017 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
| 06/30/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | INCR |
| 07/05/2017 | ROOF NAILING | BSTEVENS | Approved | |
| 07/05/2017 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 10/09/2017 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 10/09/2017 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
| 10/09/2017 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 10/09/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
| 10/09/2017 | FRAMING | JBURGE | Approved | |
| 10/23/2017 | STUCCO MESH | JBURGE | Approved | |
| 04/11/2018 | MECHANICAL - FINAL | ESTEVEN1 | Approved | APPROVED |
| 04/11/2018 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | APPROVED |
| 04/13/2018 | GAS CLEARANCE | ESTEVENS | Approved | |
| 04/16/2018 | PLUMBING - FINAL | DFLORES2 | Approved | |
| 04/16/2018 | BUILDING - FINAL | DFLORES2 | Approved | |
| 04/16/2018 | ELECTRIC - FINAL | DFLORES2 | Approved |