Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
1125 N 2ND AV
Address NEW:
1125 N 2ND AV
Apply Date:
01/12/2017
Applicant:
STERTZ CONSTRUCTION LLC
Description:
KITCHEN, BATH & BEDROOM ADDITION
Contractors:
  • STERTZ CONSTRUCTION LLC

Permit Reviews

Permit Number - T17CM00270
Permit Status: Final
Permit Description: KITCHEN, BATH & BEDROOM ADDITION
Start Date Submittal Complete Date Status  
01/12/2017 RESIDENTIAL - BLDG/ZONING-WALKTHRU 01/12/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM00270
Permit Status: Final
Permit Description: KITCHEN, BATH & BEDROOM ADDITION
Total Outstanding Activity Conditions - 1
Date Name
01/12/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM00270
Permit Description: KITCHEN, BATH & BEDROOM ADDITION
Total Completed Inspections - 16
Date Description Inspector Results Comments
02/10/2017 EXCAVATION/LAYOUT REBAR & ZON BSTEVENS Approved
02/23/2017 PLUMBING - ROUGH, SOIL BSTEVENS Approved
02/28/2017 BUILDING PRE-SLAB BSTEVENS Approved
03/30/2017 U VALUE FOR WINDOW wnorth Approved
04/04/2017 PLUMBING - GAS PRESSURE TEST BSTEVENS Approved
04/04/2017 PLUMBING - INTERMEDIATE BSTEVENS Approved
04/04/2017 ELECTRIC - INTERMEDIATE BSTEVENS Approved
04/04/2017 FRAMING BSTEVENS Approved
04/04/2017 EXT METAL CLIPS/EXT SHEATHING BSTEVENS Approved
04/04/2017 ROOF NAILING BSTEVENS Approved
04/07/2017 MECHANICAL - INTERMEDIATE north Approved
04/14/2017 STUCCO MESH BSTEVENS Approved
05/19/2017 PLUMBING - FINAL NORTH Approved
05/19/2017 ELECTRIC - FINAL NORTH Approved
11/19/2020 MECHANICAL - FINAL ESTEVENS Approved
11/19/2020 BUILDING - FINAL ESTEVENS Approved