Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T16CM09210
Permit Details
Apply Date:
12/09/2016
Applicant:
VENEZIANO, PHILIP JOHN
Description:
ELECTRICAL
Architects:
- VENEZIANO, PHILIP JOHN
Contractors:
- BETTER BUILT BUILDERS INC *
Permit Reviews
Permit Number - T16CM09210
Permit Status: L of c
Permit Description: ELECTRICAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/20/2017 | REVISION - - 2ND | 01/23/2017 | COMPLETED |
02/06/2017 | REVISION - - 3RD | 02/06/2017 | COMPLETED |
02/06/2017 | REVISION - - 3RD | 02/14/2017 | COMPLETED |
02/14/2017 | REVISION - - 3RD | 02/17/2017 | COMPLETED |
03/06/2017 | REVISION - - 4TH | 03/07/2017 | COMPLETED |
12/09/2016 | COMMERCIAL - TI | 12/23/2016 | COMPLETED |
12/27/2016 | REVISION - - 1ST | 01/04/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM09210
Permit Status: L of c
Permit Description: ELECTRICAL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/09/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T16CM09210
Permit Description: ELECTRICAL
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/30/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
01/30/2017 | FRAMING | ESTEVEN1 | Approved | APPROVED |
02/22/2017 | PLUMBING - PROGRESS | MPUGH1 | Approved | IVRS - Inspection :*LF1 power cover area ok. phase 2 ok. |
04/10/2017 | FIRE SPKLR - FINAL | north | Approved | |
04/10/2017 | FIRE SPKLR - FINAL | north | Approved | |
04/26/2017 | MECHANICAL - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
04/26/2017 | PLUMBING - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
06/07/2017 | FIRE - ALARM FINAL | jdonovan | Approved | |
06/07/2017 | FIRE - FINAL | jdonovan | Approved | |
06/07/2017 | ELECTRIC - INTERMEDIATE | mpugh1 | Approved | |
06/07/2017 | ELECTRIC - ABOVE CEILING | mpugh1 | Approved | |
06/07/2017 | ELECTRIC - FINAL | mpugh1 | Approved | |
06/07/2017 | PLUMBING - ROUGH, SOIL | mpugh1 | Approved | |
06/07/2017 | PLUMBING - FINAL | mpugh1 | Approved | |
06/07/2017 | MECHANICAL - FINAL | mpugh1 | Approved | |
06/07/2017 | BUILDING ABOVE CEILING | mpugh1 | Approved | |
06/07/2017 | MECHANICAL - ABOVE CEILING | mpugh1 | Approved | |
06/08/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
06/22/2017 | BUILDING - FINAL | mpugh1 | Approved | AIR BALANCE REPORT SENT TO RECORDS |