Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T16CM08973
Permit Details
Apply Date:
11/30/2016
Applicant:
VANCE GOODMAN
Description:
NEW APARTMENTS
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T16CM08973
Permit Status: C of o
Permit Description: NEW APARTMENTS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/12/2017 | RESUBMITTAL | 05/02/2017 | COMPLETED |
03/08/2018 | REVISION - - 3RD | 03/08/2018 | COMPLETED |
09/08/2017 | WALK THRU - COMM | 09/13/2017 | COMPLETED |
11/30/2016 | COMMERCIAL - NEW | 11/30/2016 | COMPLETED |
11/30/2016 | RESUBMITTAL | 12/21/2016 | COMPLETED |
11/30/2017 | REVISION - - 1ST | 12/07/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM08973
Permit Status: C of o
Permit Description: NEW APARTMENTS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/30/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM08973
Permit Description: NEW APARTMENTS
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/14/2018 | SITE - SEWER | ESTEVEN1 | Approved | APPROVED FROM DOUBLE CLEAN OUT TO PRIVATE SEWER CONNECTION. |
05/14/2018 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED FROM DOUBLE CLEAN OUT TO PRIVATE SEWER CONNECTION. |
05/17/2018 | PLUMBING - PRE SLAB | ESTEVEN1 | Approved | APPROVED |
05/17/2018 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
05/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
06/15/2018 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | APPROVED ALL UNITS, FROM TRANSFORMER TO METER PACK. |
06/21/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED |
06/21/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | |
07/10/2018 | PLUMBING - ROOF DRAINS | ESTEVEN1 | Approved | APPROVED |
07/26/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
07/26/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
07/26/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
07/26/2018 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
07/30/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
07/30/2018 | FRAMING | ESTEVEN1 | Approved | APPROVED |
08/14/2018 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
08/14/2018 | STUCCO MESH | ESTEVEN1 | Approved | APPROVED |
08/28/2018 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | BUILBING #3 UNIT 1 THRU 7 PLUS HOUSE METER. |
08/29/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | ECO BUILDING #3, 3101 3102 3103 3104 3105 3106 3107 & HOUSE METER |
09/13/2018 | FIRE SPKLR - FINAL | jvincent | Approved | |
09/13/2018 | FIRE - ALARM FINAL | jvincent | Approved | |
09/13/2018 | ENGINEERING - FINAL | bbenedo1 | Approved | |
09/13/2018 | LANDSCAPE - FINAL | bbenedo1 | Approved | |
09/13/2018 | SIGN - FINAL | bbenedo1 | Approved | |
09/13/2018 | NPPO - FINAL | bbenedo1 | Approved | |
09/14/2018 | FIRE - FINAL | jvincent | Approved | -will place knox lock on back gate upon leaving the job. |
09/14/2018 | MECHANICAL - FINAL | ESTEVENS | Approved | pending other inspections, including wall inspections and development package. |
09/14/2018 | ELECTRIC - FINAL | ESTEVENS | Approved | pending other inspections, including wall inspections and development package. |
09/17/2018 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | |
09/17/2018 | MECHANICAL - PROGRESS | ESTEVEN1 | Approved | |
09/17/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | |
09/17/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | |
09/17/2018 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | |
09/17/2018 | ELECTRIC - UFER | ESTEVEN1 | Approved | |
09/17/2018 | BUILDING - PROGRESS | ESTEVEN1 | Approved | |
09/17/2018 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | |
09/17/2018 | REINFORCED MASONRY PRE-GROUT | ESTEVEN1 | Approved | |
09/17/2018 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | |
09/18/2018 | ROOF NAILING | ESTEVENS | Approved | |
09/21/2018 | BUILDING - FINAL | ESTEVEN1 | Approved | |
09/21/2018 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVEN1 | Approved | |
09/21/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | |
09/21/2018 | RIGHT OF WAY - FINAL | DROBERTSON | Approved | |
09/21/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |