Permit: T16CM08574
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
1101 N WILMOT RD #115
Address NEW:
1101 N WILMOT RD #115
Apply Date:
11/14/2016
Applicant:
CALL, GRANT CITY SPACEWS ARCHITECTURE
Description:
TI; DENTAL OFFICE
Architects:
- CALL, GRANT
Permit Reviews
Permit Number - T16CM08574
Permit Status: C of o
Permit Description: TI; DENTAL OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2017 | RESUBMITTAL | 01/20/2017 | COMPLETED |
| 01/20/2017 | RESUBMITTAL - TI ALL | 01/20/2017 | COMPLETED |
| 11/14/2016 | PLANS OK TO SUBMIT - COMM | 11/14/2016 | COMPLETED |
| 11/14/2016 | COMMERCIAL - TI | 12/21/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM08574
Permit Status: C of o
Permit Description: TI; DENTAL OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/14/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM08574
Permit Description: TI; DENTAL OFFICE
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
| 01/23/2017 | PLUMBING - PRE SLAB | ESTEVEN1 | Approved | APPROVED |
| 01/23/2017 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | UNDER GROUND |
| 01/31/2017 | MECHANICAL - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/10/2017 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | |
| 02/10/2017 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | |
| 02/10/2017 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | |
| 02/17/2017 | BUILDING - PROGRESS | ESTEVEN1 | Approved | SHEET ROCK |
| 03/13/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | |
| 03/13/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | |
| 03/16/2017 | RIGHT OF WAY - FINAL | tadkins | Approved | |
| 03/16/2017 | NPPO - FINAL | RLEDONNE | Approved | |
| 03/16/2017 | SIGN - FINAL | RLEDONNE | Approved | |
| 03/16/2017 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 03/16/2017 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 03/17/2017 | FRAMING | TVALENC1 | Approved | |
| 03/17/2017 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | |
| 03/17/2017 | PLUMBING - PROGRESS | TVALENC1 | Approved | |
| 03/28/2017 | BUILDING - FINAL | TVALENC1 | Approved | |
| 03/28/2017 | ELECTRIC - SERVICE UPGRADE | TVALENC1 | Approved | |
| 03/28/2017 | ELECTRIC - FINAL | TVALENC1 | Approved | |
| 03/28/2017 | PLUMBING - FINAL | TVALENC1 | Approved | |
| 03/28/2017 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | |
| 03/28/2017 | MECHANICAL - FINAL | TVALENC1 | Approved | |
| 03/29/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 03/30/2017 | FIRE - FINAL | jvincent | Approved |