Permit: T16CM08526
Permit Details
Apply Date:
11/10/2016
Applicant:
COLBY MOELLER
Description:
SORORITY HOUSE
Architects:
- COLBY MOELLER
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T16CM08526
Permit Status: C of o
Permit Description: SORORITY HOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/11/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 05/03/2017 | COMPLETED |
| 11/10/2016 | PLANS OK TO SUBMIT - COMM | 11/21/2016 | COMPLETED |
| 11/21/2016 | 3RD PARTY REVIEW - COMMERCIAL | 12/27/2016 | COMPLETED |
| 12/27/2016 | POST 3RD PARTY REVIEW | 12/28/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM08526
Permit Status: C of o
Permit Description: SORORITY HOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/10/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM08526
Permit Description: SORORITY HOUSE
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 03/10/2017 | SITE - SEWER | ESTEVEN1 | Approved | FROM ADA SECTION, HOUSE MOTHER AND OFFICERS QUARTERS, ALL TIED INTO THE MAIN SEWER. |
| 03/10/2017 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | APPROVED. FROM STUB OUT TO INTERIOR PANEL. |
| 03/22/2017 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED. ADA RAMP |
| 03/28/2017 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | APPROVED |
| 06/08/2017 | ROOF NAILING | DQUINN | Approved | |
| 06/21/2017 | FRAMING | NORTH | Approved | |
| 07/11/2017 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED. |
| 07/11/2017 | PLUMBING - BACK WATER VALVE | ESTEVEN1 | Approved | APPROVED. |
| 07/11/2017 | PLUMBING - GAS PRESSURE TEST | ESTEVEN1 | Approved | UNDER TEST AND FOR METER |
| 07/13/2017 | GAS CLEARANCE | ESTEVENS | Approved | |
| 07/25/2017 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | 2ND FLOOR |
| 07/25/2017 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | 2ND FLOOR |
| 07/25/2017 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | 2ND FLOOR |
| 07/28/2017 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | STUCCO MESH | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED. |
| 07/28/2017 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED. |
| 08/01/2017 | RIGHT OF WAY - FINAL | DR | Approved | |
| 08/03/2017 | FIRE - FINAL | JPEELDAVIS | Approved | |
| 08/03/2017 | NPPO - FINAL | DROBERTS | Approved | |
| 08/03/2017 | SIGN - FINAL | DROBERTS | Approved | |
| 08/03/2017 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 08/04/2017 | PLUMBING - GAS PRESS TEST FNL | ESTEVEN1 | Approved | |
| 08/04/2017 | OUTDOOR LIGHTING FINAL | ESTEVEN1 | Approved | APPROVED. |
| 08/04/2017 | ELECTRIC - OUTDOOR LIGHTING | ESTEVEN1 | Approved | APPROVED. |
| 08/04/2017 | ELECTRIC - UFER | ESTEVEN1 | Approved | APPROVED. |
| 11/02/2017 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
| 11/02/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 11/03/2017 | BUILDING - FINAL | RSHERRY | Approved | |
| 11/03/2017 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
| 11/03/2017 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETE |