Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Address NEW:
2450 E RIVER RD #100
Apply Date:
10/26/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI; MEDICAL OFFICE
Architects:
  • EGLIN, EVAN SAR
Contractors:
  • CAYLOR CONSTRUCTION COMPANY , RO*** APA ***

Permit Reviews

Permit Number - T16CM08122
Permit Status: L of c
Permit Description: TI; MEDICAL OFFICE
Start Date Submittal Complete Date Status  
01/17/2017 REVISION - - 1ST 01/17/2017 COMPLETED Review Details
10/26/2016 COMMERCIAL - TI 11/03/2016 COMPLETED Review Details
11/03/2016 RESUBMITTAL 01/04/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T16CM08122
Permit Status: L of c
Permit Description: TI; MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date Name
10/26/2016 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T16CM08122
Permit Description: TI; MEDICAL OFFICE
Total Completed Inspections - 19
Date Description Inspector Results Comments
01/26/2017 PLUMBING - ROUGH, SOIL BSTEVENS Approved
01/31/2017 EXCAVATION/LAYOUT REBAR & ZON BSTEVENS Approved
01/31/2017 PLUMBING - PROGRESS BSTEVENS Approved
03/10/2017 FRAMING ESTEVEN1 Approved APPROVED. ROOMS 101, 104 AND 105.
03/10/2017 ELECTRIC - INTERMEDIATE ESTEVEN1 Approved APPROVED. ROOMS 101, 104 AND 105.
03/20/2017 SHEET ROCK NAILING ESTEVEN1 Approved APPROVED
03/20/2017 MECHANICAL - ABOVE CEILING ESTEVEN1 Approved APPROVED
03/20/2017 MECHANICAL - INTERMEDIATE ESTEVEN1 Approved APPROVED
03/20/2017 PLUMBING - ABOVE CEILING ESTEVEN1 Approved APPROVED
03/20/2017 PLUMBING - INTERMEDIATE ESTEVEN1 Approved APPROVED
03/21/2017 ENGINEERING - FINAL MRUSSO Approved
03/29/2017 BUILDING ABOVE CEILING BSTEVENS Approved
03/29/2017 ELECTRIC - ABOVE CEILING BSTEVENS Approved
04/04/2017 BUILDING - FINAL BSTEVENS Approved
04/04/2017 MECHANICAL - FINAL BSTEVENS Approved
04/04/2017 PLUMBING - FINAL BSTEVENS Approved
04/04/2017 ELECTRIC - FINAL BSTEVENS Approved
04/05/2017 FIRE - FINAL CBASALDUA Approved
04/05/2017 FIRE SPKLR - FINAL CBASALDUA Approved