Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
760 N TYNDALL AV
Address NEW:
760 N TYNDALL AV
Apply Date:
10/05/2016
Applicant:
PAGE REPP
Description:
RESTAURANT
Architects:
  • PAGE REPP
Contractors:
  • REPP CONSTRUCTION

Permit Reviews

Permit Number - T16CM07611
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
01/18/2017 REVISION - - 1ST 01/18/2017 COMPLETED Review Details
10/05/2016 COMMERCIAL - TI 10/12/2016 COMPLETED Review Details
10/12/2016 RESUBMITTAL - TI ALL 11/10/2016 COMPLETED Review Details
11/17/2016 RESUBMITTAL 11/23/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T16CM07611
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
10/05/2016 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T16CM07611
Permit Description: RESTAURANT
Total Completed Inspections - 36
Date Description Inspector Results Comments
12/04/2016 PLUMBING - ROUGH, SOIL JBURGE Approved INTERIOR ROUGH SOIL - NEED TO PLACE GREASE INTERCEPTOR. OK TO COVER PROGRESS AREAS.
12/06/2016 ELECTRIC - PROGRESS JBURGE Approved ELECTRIC UNDERGROUND - CONDUITS TO COOKING ISLAND. OK TO COVER PROGRESS AREAS
12/15/2016 PLUMBING - INTERMEDIATE JBURGE Approved NORTH WALL (HOOD AREA) ALL COPPER LINES UNDER TEST. OK TO COVER WALL.
12/15/2016 ELECTRIC - INTERMEDIATE JBURGE Approved NORTH WALL (HOOD AREA) OK TO COVER.
12/18/2016 MECHANICAL - HOODS JBURGE Approved SMOKE TESTED DUCT SYSTEM - OK TO WRAP AND INSTALL.
12/22/2016 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved COLUMN FOOTINGS (3) FOR WEST CANOPY. OK TO PUR WHEN WATER HAS BEEN EVCUATED FROM POUR AREAS.
01/04/2017 SITE - SEWER JBURGE Approved ATTACHED TO MAIN SEWER (4" LINE). OK TO COVER.
01/04/2017 ROOF NAILING JBURGE Approved
01/04/2017 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved
01/12/2017 MECHANICAL - PROGRESS JBURGE Approved
01/12/2017 MECHANICAL - ABOVE CEILING JBURGE Approved
01/16/2017 FRAMING JBURGE Approved
01/16/2017 MECHANICAL - INTERMEDIATE JBURGE Approved
01/16/2017 PLUMBING - ABOVE CEILING JBURGE Approved
01/16/2017 ELECTRIC - ABOVE CEILING JBURGE Approved
02/15/2017 PLUMBING - GAS PRESS TEST FNL JBURGE Approved
03/07/2017 PLUMBING - GAS PRESSURE TEST JBURGE Approved
03/07/2017 ELECTRIC - SERVICE UPGRADE JBURGE Approved
03/07/2017 PLUMBING - PROGRESS JBURGE Approved
03/07/2017 PLUMBING - PRE SLAB JBURGE Approved
03/07/2017 U VALUE FOR WINDOW JBURGE Approved
03/07/2017 BUILDING ABOVE CEILING JBURGE Approved
03/07/2017 OUTDOOR LIGHTING FINAL JBURGE Approved
03/07/2017 ELECTRIC - OUTDOOR LIGHTING JBURGE Approved
03/08/2017 GAS CLEARANCE JBURGE Approved
03/17/2017 RIGHT OF WAY - FINAL DR Approved No R/W impact.
03/19/2017 MECHANICAL - FINAL JBURGE Approved
03/19/2017 PLUMBING - FINAL JBURGE Approved
03/19/2017 BUILDING - FINAL JBURGE Approved
03/19/2017 BUILDING - PROGRESS JBURGE Approved
03/19/2017 ELECTRIC - FINAL JBURGE Approved
03/20/2017 FIRE - FINAL CBASALDUA Approved
03/20/2017 NPPO - FINAL MRUSSO Approved
03/20/2017 SIGN - FINAL MRUSSO Approved
03/20/2017 LANDSCAPE - FINAL MRUSSO Approved
03/20/2017 ENGINEERING - FINAL MRUSSO Approved