Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T16CM07611
Permit Details
Apply Date:
10/05/2016
Applicant:
PAGE REPP
Description:
RESTAURANT
Architects:
- PAGE REPP
Contractors:
- REPP CONSTRUCTION
Permit Reviews
Permit Number - T16CM07611
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2017 | REVISION - - 1ST | 01/18/2017 | COMPLETED |
10/05/2016 | COMMERCIAL - TI | 10/12/2016 | COMPLETED |
10/12/2016 | RESUBMITTAL - TI ALL | 11/10/2016 | COMPLETED |
11/17/2016 | RESUBMITTAL | 11/23/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07611
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/05/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07611
Permit Description: RESTAURANT
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/04/2016 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | INTERIOR ROUGH SOIL - NEED TO PLACE GREASE INTERCEPTOR. OK TO COVER PROGRESS AREAS. |
12/06/2016 | ELECTRIC - PROGRESS | JBURGE | Approved | ELECTRIC UNDERGROUND - CONDUITS TO COOKING ISLAND. OK TO COVER PROGRESS AREAS |
12/15/2016 | PLUMBING - INTERMEDIATE | JBURGE | Approved | NORTH WALL (HOOD AREA) ALL COPPER LINES UNDER TEST. OK TO COVER WALL. |
12/15/2016 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | NORTH WALL (HOOD AREA) OK TO COVER. |
12/18/2016 | MECHANICAL - HOODS | JBURGE | Approved | SMOKE TESTED DUCT SYSTEM - OK TO WRAP AND INSTALL. |
12/22/2016 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | COLUMN FOOTINGS (3) FOR WEST CANOPY. OK TO PUR WHEN WATER HAS BEEN EVCUATED FROM POUR AREAS. |
01/04/2017 | SITE - SEWER | JBURGE | Approved | ATTACHED TO MAIN SEWER (4" LINE). OK TO COVER. |
01/04/2017 | ROOF NAILING | JBURGE | Approved | |
01/04/2017 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
01/12/2017 | MECHANICAL - PROGRESS | JBURGE | Approved | |
01/12/2017 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | |
01/16/2017 | FRAMING | JBURGE | Approved | |
01/16/2017 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
01/16/2017 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
01/16/2017 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
02/15/2017 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | |
03/07/2017 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
03/07/2017 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | |
03/07/2017 | PLUMBING - PROGRESS | JBURGE | Approved | |
03/07/2017 | PLUMBING - PRE SLAB | JBURGE | Approved | |
03/07/2017 | U VALUE FOR WINDOW | JBURGE | Approved | |
03/07/2017 | BUILDING ABOVE CEILING | JBURGE | Approved | |
03/07/2017 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
03/07/2017 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
03/08/2017 | GAS CLEARANCE | JBURGE | Approved | |
03/17/2017 | RIGHT OF WAY - FINAL | DR | Approved | No R/W impact. |
03/19/2017 | MECHANICAL - FINAL | JBURGE | Approved | |
03/19/2017 | PLUMBING - FINAL | JBURGE | Approved | |
03/19/2017 | BUILDING - FINAL | JBURGE | Approved | |
03/19/2017 | BUILDING - PROGRESS | JBURGE | Approved | |
03/19/2017 | ELECTRIC - FINAL | JBURGE | Approved | |
03/20/2017 | FIRE - FINAL | CBASALDUA | Approved | |
03/20/2017 | NPPO - FINAL | MRUSSO | Approved | |
03/20/2017 | SIGN - FINAL | MRUSSO | Approved | |
03/20/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
03/20/2017 | ENGINEERING - FINAL | MRUSSO | Approved |