Permit: T16CM07581
Permit Details
Apply Date:
10/04/2016
Applicant:
TOFEL CONSTRUCTION
Description:
WOMEN'S SHELTER
Contractors:
- TOFEL CONSTRUCTION
Permit Reviews
Permit Number - T16CM07581
Permit Status: C of o
Permit Description: WOMEN'S SHELTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/18/2017 | COMMERCIAL - TI | 02/02/2017 | COMPLETED |
| 02/02/2017 | RESUBMITTAL | 02/15/2017 | COMPLETED |
| 02/15/2017 | RESUBMITTAL | 02/16/2017 | COMPLETED |
| 10/04/2016 | COMMERCIAL - TI | 10/05/2016 | COMPLETED |
| 10/05/2016 | COMMERCIAL - TI | 11/21/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07581
Permit Status: C of o
Permit Description: WOMEN'S SHELTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/04/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07581
Permit Description: WOMEN'S SHELTER
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/29/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR |
| 04/12/2017 | MECHANICAL - PROGRESS | ZMRAMBER | Approved | IVRS - Inspection :* |
| 04/12/2017 | ELECTRIC - SERVICE UPGRADE | ZMRAMBER | Approved | IVRS - Inspection :* |
| 04/12/2017 | FRAMING | ZMRAMBER | Approved | IVRS - Inspection :* |
| 04/13/2017 | PLUMBING - GAS PRESS TEST FNL | ZMRAMBER | Approved | IVRS - Inspection :* |
| 04/14/2017 | GAS CLEARANCE | MRAMBER | Approved | |
| 04/20/2017 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - TEMPORARY SERVICE | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - CONSTRUCTION POWER | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - PROGRESS | mramber1 | Approved | |
| 04/20/2017 | BUILDING ABOVE CEILING | mramber1 | Approved | |
| 04/20/2017 | BUILDING - PROGRESS | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - PRE SLAB | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - YARD WTR LINE/TEST | mramber1 | Approved | |
| 04/20/2017 | SITE - SEWER | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - PROGRESS | mramber1 | Approved | |
| 04/20/2017 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
| 04/20/2017 | PLUMBING - GAS PRESSURE TEST | mramber1 | Approved | |
| 04/20/2017 | ELECTRIC - UFER | mramber1 | Approved | |
| 04/21/2017 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 04/21/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 04/25/2017 | MECHANICAL - HOODS | MRAMBER1 | Approved | IVRS - Inspection :* |
| 04/25/2017 | OUTDOOR LIGHTING FINAL | MRAMBER1 | Approved | IVRS - Inspection :* |
| 04/25/2017 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER1 | Approved | IVRS - Inspection :* |
| 04/25/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 04/27/2017 | ELECTRIC - FINAL | mramber1 | Approved | |
| 04/27/2017 | PLUMBING - FINAL | mramber1 | Approved | |
| 04/27/2017 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
| 05/11/2017 | MECHANICAL - FINAL | mramber1 | Approved | |
| 05/12/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 05/12/2017 | BUILDING - FINAL | DROBERTS | Approved |