Permit: T16CM07260
Permit Details
Apply Date:
09/21/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW RETAIL SHELL BLDG
Contractors:
- RYAN COMPANIES U S INC
Permit Reviews
Permit Number - T16CM07260
Permit Status: Final
Permit Description: NEW RETAIL SHELL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/27/2017 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 03/27/2017 | ACTIVE |
| 04/13/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 07/28/2017 | COMPLETED |
| 09/21/2016 | PLANS OK TO SUBMIT - COMM | 09/26/2016 | COMPLETED |
| 09/23/2016 | 3RD PARTY REVIEW - COMMERCIAL | 10/04/2016 | COMPLETED |
| 10/04/2016 | RESUBMITTAL | 10/07/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07260
Permit Status: Final
Permit Description: NEW RETAIL SHELL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/21/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T16CM07260
Permit Description: NEW RETAIL SHELL BLDG
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/29/2017 | ELECTRIC - UNDERGROUND | bbenedon | Approved | primary raceways |
| 05/22/2017 | BUILDING PRE-SLAB | bbenedon | Approved | |
| 05/22/2017 | ROOF NAILING | bbenedon | Approved | |
| 05/22/2017 | U VALUE FOR WINDOW | bbenedon | Approved | |
| 05/22/2017 | MECHANICAL - INTERMEDIATE | bbenedon | Approved | |
| 05/22/2017 | PLUMBING - ROUGH, SOIL | bbenedon | Approved | |
| 05/22/2017 | PLUMBING - INTERMEDIATE | bbenedon | Approved | |
| 05/24/2017 | MECHANICAL - ABOVE CEILING | bbenedon | Approved | |
| 05/24/2017 | ELECTRIC - OUTDOOR LIGHTING | bbenedon | Approved | |
| 05/24/2017 | ELECTRIC - INTERMEDIATE | bbenedon | Approved | |
| 05/24/2017 | FRAMING | bbenedon | Approved | |
| 05/24/2017 | EXT METAL CLIPS/EXT SHEATHING | bbenedon | Approved | |
| 06/06/2017 | ELECTRIC - UFER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/07/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 06/27/2017 | SITE - SEWER | bbenedon | Approved | |
| 06/27/2017 | PLUMBING - FINAL | bbenedon | Approved | |
| 06/27/2017 | MECHANICAL - FINAL | bbenedon | Approved | |
| 06/27/2017 | STUCCO MESH | bbenedon | Approved | |
| 06/29/2017 | PLUMBING - ROOF DRAINS | bbenedon | Approved | |
| 07/20/2017 | OUTDOOR LIGHTING FINAL | bbenedon | Approved | |
| 07/20/2017 | ELECTRIC - FINAL | bbenedon | Approved | |
| 07/21/2017 | FIRE - FINAL | jvincent | Approved | Shell only. |
| 07/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | |
| 07/26/2017 | BUILDING - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/27/2017 | NPPO - FINAL | MRUSSO | Approved | |
| 07/27/2017 | SIGN - FINAL | MRUSSO | Approved | |
| 07/27/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 07/27/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/01/2017 | RIGHT OF WAY - FINAL | TW | Approved |