Permit: T16CM07213
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
101 E FORT LOWELL RD
Address NEW:
101 E FORT LOWELL RD
Apply Date:
09/20/2016
Applicant:
BOHN, STEPHEN CHARLES
Description:
RESTAURANT
Architects:
- BOHN, STEPHEN CHARLES
Contractors:
- HARTMAN CONSTRUCTION LLC
Permit Reviews
Permit Number - T16CM07213
Permit Status: C of o
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2017 | REVISION - - 1ST | 01/25/2017 | COMPLETED |
| 05/08/2017 | REVISION - - 2ND | 05/08/2017 | COMPLETED |
| 09/20/2016 | COMMERCIAL - TI | 09/22/2016 | COMPLETED |
| 09/22/2016 | COMMERCIAL - TI | 10/17/2016 | COMPLETED |
| 11/08/2016 | RESUBMITTAL - TI ALL | 12/13/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07213
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/20/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07213
Permit Description: RESTAURANT
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2017 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 01/25/2017 | REINFORCED MASONRY PRE-GROUT | ESTEVEN1 | Approved | APPROVED |
| 01/25/2017 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | APPROVED |
| 01/30/2017 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 01/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 01/31/2017 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 01/31/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 02/10/2017 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
| 03/01/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
| 03/01/2017 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | |
| 03/01/2017 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
| 03/01/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 03/01/2017 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 03/01/2017 | FRAMING | BSTEVENS | Approved | |
| 03/01/2017 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 03/08/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 03/08/2017 | STUCCO MESH | BSTEVENS | Approved | |
| 03/16/2017 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | SMOKE TEST FOR HOOD DUCT - OK. TO BE DOUBLE INSULATION WRAPPED. DUCT SYSTEM COMPLETE AND IN PLACE. |
| 04/21/2017 | ELECTRIC - ABOVE CEILING | NORTH | Approved | |
| 05/02/2017 | MECHANICAL - FINAL | JJaworsky | Approved | |
| 05/02/2017 | PLUMBING - FINAL | JJaworsky | Approved | |
| 05/02/2017 | ELECTRIC - FINAL | JJaworsky | Approved | |
| 05/09/2017 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
| 05/09/2017 | BUILDING - PROGRESS | BSTEVENS | Approved | |
| 05/09/2017 | BUILDING ABOVE CEILING | BSTEVENS | Approved | |
| 05/11/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 05/12/2017 | CERTIFICATE OF OCCUPANCY | bstevens | Approved | |
| 05/12/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 05/12/2017 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
| 05/12/2017 | MECHANICAL - HOODS | BSTEVENS | Approved | |
| 05/12/2017 | PLUMBING - PROGRESS | BSTEVENS | Approved | |
| 05/12/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
| 05/12/2017 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 05/12/2017 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
| 05/12/2017 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 05/12/2017 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
| 05/12/2017 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 05/12/2017 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 05/12/2017 | BUILDING - FINAL | BSTEVENS | Approved |