Permit: T16CM07135
Permit Details
Apply Date:
09/15/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CAR DEALERSHIP
Architects:
- BARCUS, BARRY RAY
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T16CM07135
Permit Status: C of o
Permit Description: CAR DEALERSHIP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/05/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 10/30/2017 | COMPLETED |
09/15/2016 | PLANS OK TO SUBMIT - COMM | 09/19/2016 | COMPLETED |
09/19/2016 | 3RD PARTY REVIEW - COMMERCIAL | 10/13/2016 | COMPLETED |
10/13/2016 | POST 3RD PARTY REVIEW | 10/18/2016 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T16CM07135
Permit Status: C of o
Permit Description: CAR DEALERSHIP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/15/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07135
Permit Description: CAR DEALERSHIP
Total Completed Inspections - 40
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/20/2017 | PLUMBING - ROUGH, SOIL | MPUGH1 | Approved | IVRS - Inspection :* |
02/02/2017 | BUILDING PRE-SLAB | MPUGH1 | Approved | IVRS - Inspection :* |
02/02/2017 | STEM WALL/RETAINING WALL | MPUGH1 | Approved | IVRS - Inspection :* |
05/17/2017 | ROOF NAILING | mpugh1 | Approved | |
06/13/2017 | PLUMBING - ROOF DRAINS | MPUGH1 | Approved | IVRS - Inspection :* |
06/23/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | WATER FEED IS FROM THE EXISTING BUILDING TO THE SOUTH |
06/23/2017 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
06/29/2017 | ELECTRIC - UNDERGROUND | MPUGH1 | Approved | IVRS - Inspection :* |
07/17/2017 | ELECTRIC - UFER | mpugh1 | Approved | |
07/26/2017 | PLUMBING - BACK WATER VALVE | MPUGH1 | Approved | IVRS - Inspection :* |
09/06/2017 | SHEET ROCK NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
10/25/2017 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
10/25/2017 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
10/26/2017 | MECHANICAL - FINAL | NORTH | Approved | |
10/26/2017 | PLUMBING - FINAL | NORTH | Approved | |
10/26/2017 | ELECTRIC - FINAL | NORTH | Approved | |
10/26/2017 | PLUMBING - FINAL | ESTEVEN1 | Approved | |
10/30/2017 | PLUMBING - SEWER HCS CONNECT | BBENEDO1 | Approved | IVRS - Inspection :* |
10/30/2017 | OUTDOOR LIGHTING FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
10/30/2017 | ELECTRIC - OUTDOOR LIGHTING | BBENEDO1 | Approved | IVRS - Inspection :* |
10/30/2017 | U VALUE FOR WINDOW | BBENEDO1 | Approved | IVRS - Inspection :* |
10/31/2017 | SITE - SEWER | RGREENE | Approved | |
10/31/2017 | PLUMBING - ABOVE CEILING | RGREENE | Approved | |
10/31/2017 | BUILDING ABOVE CEILING | RGREENE | Approved | |
10/31/2017 | FRAMING | RGREENE | Approved | |
11/01/2017 | PLUMBING - GAS PRESS TEST FNL | RGREENE1 | Approved | |
11/01/2017 | PLUMBING - GAS PRESSURE TEST | RGREENE1 | Approved | |
11/01/2017 | ELECTRIC - INTERMEDIATE | RGREENE1 | Approved | |
11/01/2017 | ELECTRIC - ABOVE CEILING | RGREENE1 | Approved | |
11/01/2017 | ELECTRIC - ABOVE CEILING | RGREENE1 | Approved | |
11/02/2017 | FIRE - FINAL | JPEELDAVIS | Approved | |
11/02/2017 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
11/07/2017 | NPPO - FINAL | MRUSSO | Approved | |
11/07/2017 | SIGN - FINAL | MRUSSO | Approved | |
11/07/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
12/17/2018 | BUILDING - FINAL | BJONES | Approved | inspection has already been completed |
12/17/2018 | EXT METAL CLIPS/EXT SHEATHING | BJONES | Approved | inspection has already been completed |
12/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | inspection has already been completed |
12/17/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
12/17/2018 | RIGHT OF WAY - FINAL | BMONG | Approved | ALL THE WORK IN THE RIGHT OF WAY IS TO STANDARDS |