Permit: T16CM06649
Permit Details
Apply Date:
08/29/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
MEDICAL OFFICE
Architects:
- HIGHTON COMPANY
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T16CM06649
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/29/2016 | PLANS OK TO SUBMIT - COMM | 08/29/2016 | COMPLETED |
08/29/2016 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/15/2016 | COMPLETED |
09/15/2016 | 3RD PARTY REVIEW - COMMERCIAL | 09/21/2016 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T16CM06649
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/29/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM06649
Permit Description: MEDICAL OFFICE
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/23/2016 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
12/06/2016 | BUILDING PRE-SLAB | bbenedon | Approved | |
01/27/2017 | ELECTRIC - ABOVE CEILING | bbenedon | Approved | |
02/06/2017 | ELECTRIC - INTERMEDIATE | bbenedon | Approved | |
02/10/2017 | SHEET ROCK NAILING | BBENEDON | Approved | IVRS - Inspection :* |
02/10/2017 | FRAMING | BBENEDON | Approved | IVRS - Inspection :* |
02/10/2017 | FRAMING | BBENEDON | Approved | IVRS - Inspection :* |
02/16/2017 | PLUMBING - INTERMEDIATE | bbenedon | Approved | |
03/28/2017 | PLUMBING - ABOVE CEILING | bbenedon | Approved | |
03/30/2017 | BUILDING ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
03/30/2017 | MECHANICAL - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
03/30/2017 | MECHANICAL - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
05/12/2017 | MECHANICAL - FINAL | DQUINN | Approved | ALL MECH. AND PLUMB. TESTING IS COMPLETE AND OK |
05/12/2017 | PLUMBING - FINAL | DQUINN | Approved | |
05/12/2017 | ELECTRIC - FINAL | DQUINN | Approved | |
05/12/2017 | RIGHT OF WAY - FINAL | pcanniz1 | Approved | No Issues Right of Way. |
05/18/2017 | NPPO - FINAL | DROBERTS | Approved | |
05/18/2017 | SIGN - FINAL | DROBERTS | Approved | |
05/18/2017 | LANDSCAPE - FINAL | DROBERTS | Approved | |
05/18/2017 | FIRE - FINAL | jvincent | Approved | |
05/19/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
05/22/2017 | BUILDING - FINAL | NORTH | Approved | ALL SPPROVED FIRE,ENGINEERING,LANDSCAPE,SIGN AND NPPO |