Permit: T16CM06542
Permit Details
Apply Date:
08/23/2016
Applicant:
LANNING, ROBERT SCOTT
Description:
SFR
Architects:
- LANNING, ROBERT SCOTT
Contractors:
- G 2 CONTRACTING L L C
Permit Reviews
Permit Number - T16CM06542
Permit Status: C of o
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2017 | REVISION - - 1ST | 02/02/2017 | COMPLETED |
| 08/23/2016 | PLANS OK TO SUBMIT - RES | 08/23/2016 | COMPLETED |
| 08/23/2016 | RESIDENTIAL - BLDG/WWM | 09/30/2016 | COMPLETED |
| 09/30/2016 | RESUBMITTAL | 10/11/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM06542
Permit Status: C of o
Permit Description: SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/23/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM06542
Permit Description: SFR
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/14/2016 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | APPROVED, INSTALLED A TEMP. POLE |
| 12/15/2016 | TEP CLEARANCE - AM | ESTEVENS | Approved | TMPP |
| 01/05/2017 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 01/05/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | |
| 01/10/2017 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | |
| 01/18/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 01/23/2017 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 01/23/2017 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 02/14/2017 | ROOF NAILING | BSTEVENS | Approved | |
| 02/14/2017 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 02/22/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
| 02/22/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
| 02/22/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 02/22/2017 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
| 02/24/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
| 02/24/2017 | FRAMING | BSTEVENS | Approved | |
| 02/28/2017 | STUCCO MESH | BSTEVENS | Approved | |
| 03/08/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
| 04/13/2017 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 04/13/2017 | ELECTRIC - CABLE DROP | BSTEVENS | Approved | |
| 05/22/2017 | BUILDING - FINAL | BSTEVENS | Approved | |
| 05/22/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 05/22/2017 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
| 05/22/2017 | PLUMBING - GAS PRESS TEST FNL | BSTEVENS | Approved | |
| 05/22/2017 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 05/22/2017 | MECHANICAL - FINAL | BSTEVENS | Approved | |
| 05/23/2017 | GAS CLEARANCE | BSTEVENS | Approved |