Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T16CM06462
Permit Details
Apply Date:
08/19/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RESTAURANT
Contractors:
- NATIONAL CONSTRUCTION MANAGEMENT INC
Permit Reviews
Permit Number - T16CM06462
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/19/2016 | PLANS OK TO SUBMIT - COMM | 08/19/2016 | COMPLETED |
08/19/2016 | COMMERCIAL - TI | 10/31/2016 | COMPLETED |
10/31/2016 | RESUBMITTAL | 11/08/2016 | COMPLETED |
11/08/2016 | RESUBMITTAL | 11/23/2016 | COMPLETED |
11/23/2016 | RESUBMITTAL | 11/30/2016 | COMPLETED |
12/14/2016 | REVISION - - 1ST | 12/14/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM06462
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/19/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM06462
Permit Description: RESTAURANT
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2016 | PLUMBING - PRE SLAB | JMILITE1 | Approved | OK TO BACKFILL DWV INSIDE BLDG. STILL NEED TO SEE GREASE TRAP. |
12/27/2016 | BUILDING PRE-SLAB | TVALENC1 | Approved | 1- 550 GALLON GREASE INTERCEPTOR HAS BEEN FILLED WITH WATER AND IS OKAY FOR BACKFILL AROUND INTERCEPTOR ONLY. |
01/19/2017 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
01/19/2017 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
01/19/2017 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
01/24/2017 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | IVRS - Inspection :* |
01/24/2017 | ELECTRIC - TEMPORARY SERVICE | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
02/14/2017 | MECHANICAL - HOODS | TVALENC1 | Approved | IVRS - Inspection :* |
02/22/2017 | PLUMBING - GAS PRESS TEST FNL | TVALENC1 | Approved | IVRS - Inspection :* |
02/22/2017 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
02/22/2017 | PLUMBING - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
02/22/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
02/22/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
02/23/2017 | GAS CLEARANCE | TVALENCIA | Approved | |
03/01/2017 | LANDSCAPE - FINAL | DROBERTS | Approved | |
03/01/2017 | SIGN - FINAL | DROBERTS | Approved | |
03/01/2017 | NPPO - FINAL | DROBERTS | Approved | |
03/01/2017 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | MECHANICAL - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | MECHANICAL - HOOD SYSTEMS | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | PLUMBING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | ELECTRIC - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | ELECTRIC - SERVICE UPGRADE | TVALENC1 | Approved | IVRS - Inspection :* |
03/01/2017 | BUILDING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
03/02/2017 | RIGHT OF WAY - FINAL | tadkins | Approved | |
03/03/2017 | BUILDING - FINAL | TVALENC1 | Approved | |
03/07/2017 | FIRE - FINAL | jvincent | Approved | will call us in a few weeks to place key in lock box. |
03/08/2017 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | |
03/15/2017 | ENGINEERING - FINAL | RLEDONNE | Approved | PER PHONE |