Permit: T16CM05889
Permit Details
Apply Date:
07/27/2016
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT25S13 T13-M0007
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T16CM05889
Permit Status: Final
Permit Description: SFR RICHT25S13 T13-M0007
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/27/2016 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 07/27/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM05889
Permit Status: Final
Permit Description: SFR RICHT25S13 T13-M0007
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/27/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T16CM05889
Permit Description: SFR RICHT25S13 T13-M0007
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/10/2016 | PLUMBING - SEWER HCS CONNECT | MPUGH1 | Approved | IVRS - Inspection :* |
08/10/2016 | PLUMBING - YARD WTR LINE/TEST | MPUGH1 | Approved | IVRS - Inspection :* |
08/10/2016 | PLUMBING - ROUGH, SOIL | MPUGH1 | Approved | IVRS - Inspection :* |
08/18/2016 | BUILDING PRE-SLAB | MPUGH1 | Approved | IVRS - Inspection :* |
08/18/2016 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH1 | Approved | IVRS - Inspection :* |
09/15/2016 | ROOF NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
09/15/2016 | EXT METAL CLIPS/EXT SHEATHING | MPUGH1 | Approved | IVRS - Inspection :* |
10/11/2016 | PLUMBING - GAS PRESSURE TEST | bbenedo | Approved | |
10/12/2016 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
10/12/2016 | PLUMBING - INTERMEDIATE | bbenedo | Approved | |
10/12/2016 | ELECTRIC - INTERMEDIATE | bbenedo | Approved | |
10/12/2016 | ELECTRIC - UFER | bbenedo | Approved | |
10/12/2016 | ELECTRIC - CABLE DROP | bbenedo | Approved | |
10/12/2016 | U VALUE FOR WINDOW | bbenedo | Approved | |
10/12/2016 | STUCCO MESH | bbenedo | Approved | |
10/12/2016 | FRAMING | bbenedo | Approved | |
10/13/2016 | MECHANICAL - INTERMEDIATE | BBENEDO | Approved | |
10/24/2016 | SHEET ROCK NAILING | BBENEDO | Approved | |
11/18/2016 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
11/22/2016 | GAS CLEARANCE | BBENEDON | Approved | |
11/23/2016 | ELECTRIC - TEMPORARY SERVICE | BBENEDON | Approved | IVRS - Inspection :* |
11/23/2016 | OUTDOOR LIGHTING FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/23/2016 | MECHANICAL - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/23/2016 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/23/2016 | ELECTRIC - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/23/2016 | BUILDING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |