Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Address:
414 N 5TH AV
Apply Date:
07/25/2016
Applicant:
Scott Cummings
Description:
TI: RESTAURANT

Permit Reviews

Permit Number - T16CM05829
Permit Status: Issued
Permit Description: TI: RESTAURANT
Start Date Submittal Complete Date Status  
07/25/2016 COMMERCIAL - TI 08/03/2016 COMPLETED Review Details
08/03/2016 COMMERCIAL - TI 08/30/2016 COMPLETED Review Details
09/29/2016 RESUBMITTAL - TI ALL 10/31/2016 COMPLETED Review Details
10/31/2016 RESUBMITTAL - TI ALL 11/29/2016 COMPLETED Review Details
11/29/2016 RESUBMITTAL 12/21/2016 COMPLETED Review Details
12/21/2016 RESUBMITTAL 05/02/2017 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T16CM05829
Permit Status: Issued
Permit Description: TI: RESTAURANT
Total Outstanding Activity Conditions - 2
Date Name
07/25/2016 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
08/29/2016 SPECIAL INSPECTION REQUIRED FOR THE SERVICE EQUIPMENT AS NOTED ON THE ONE LINE DIAGRAM PLAN SHEET E1.

Outstanding Inspections

Permit Status: Issued
Permit Number: T16CM05829
Permite Description: TI: RESTAURANT
Total Outstanding Inspections - 25
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCPL - Gas Pressure Test N/A Not Ready
10/26/2022 COT - LCBU - Building Above Ceiling N/A Not Ready
10/27/2022 COT - LCBU - Building Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Progress N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 SITE - Zoning Final N/A Not Ready
10/27/2022 ENGR Engineering Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Above Ceiling N/A Not Ready
10/26/2022 COT - LCBU - Sustainability N/A Not Ready
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - ENGR - Site - Assurance Release N/A Not Ready
10/26/2022 COT - LCPL - Yard Water Line N/A Not Ready
10/26/2022 COT - LCPL - Sewer N/A Not Ready
10/26/2022 COT - LCBU - CofO N/A Not Ready
10/26/2022 COT - LCEL - Grounding/Bonding N/A Not Ready
10/26/2022 COT - LCPL - Backwater Valve N/A Not Ready
10/26/2022 COT - LCEL - Construction Power N/A Not Ready
10/26/2022 COT - LCEL - Temporary Service N/A Not Ready
10/27/2022 COT - LCEL - Electrical Final N/A Not Ready
10/26/2022 COT - LCEL - Outdoor Lighting N/A Not Ready
10/26/2022 COT - LCBU - Building Progress N/A Not Ready
10/26/2022 COT - LCEL - Electrical Underground N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T16CM05829
Permit Description: TI: RESTAURANT
Total Completed Inspections - 11
Date Description Inspector Results Comments
04/03/2018 COT - LCBU - Framing Passed {Activity date: 04/03/2018; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - }
09/04/2018 COT - LCEL - Electrical Intermediate Passed {Activity date: 09/04/2018; Status: Approved; Inspector: BJONES; Comment: Entered by CMURPHY1 - } ; {Activity date: 08/31/2018; Status: Denied; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - MISSING GROUND SCREWS
PLUMBING IS NOT UNDER TEST}
09/05/2018 COT - LCPL - Plumbing Intermediate Passed {Activity date: 09/05/2018; Status: Approved; Inspector: ESTEVENS; Comment: Entered by CMURPHY1 - } ; {Activity date: 09/04/2018; Status: Partial Approval; Inspector: BJONES; Comment: Entered by CMURPHY1 - Fill DWV with water for test, secure closet flanges to floor, strap bottom plates where pipes are located to protect from nails or screws.
} ; {Activity date: 08/31/2018; Status: Denied; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - MISSING GROUND SCREWS
PLUMBING IS NOT UNDER TEST}
01/11/2019 COT - HCBU - Interior Shear Bracing Passed {Activity date: 01/11/2019; Status: Approved; Inspector: ESTEVENS; Comment: Entered by CBELL1 - }
08/27/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 08/27/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER}
02/28/2023 COT - LCEL - Electrical Progress Passed
02/28/2023 COT - LCEL - Electrical Final Passed Electric final to include 02036 electric above ceiling, 02005 electric ufer, 02061 temporary construction power. The above inspections have been approved.
02/28/2023 COT - LCEL - Outdoor Lighting Passed
11/13/2023 COT - LCPL - Rough Soil Passed Grease interceptor installed. Ok to cover progress areas.
10/01/2024 COT - LCEL - Electrical Underground Passed
10/01/2024 COT - LCPL - Plumbing Final Passed

Documents

File Name Document Type  
001_COVER SHEET.TIF CONSTRPLANS VIEW
002_A0.1.TIF CONSTRPLANS VIEW
003_A0.2.TIF CONSTRPLANS VIEW
004_SP1.TIF CONSTRPLANS VIEW
005_SP2.TIF CONSTRPLANS VIEW
006_A2.0.TIF CONSTRPLANS VIEW
007_A3.0.TIF CONSTRPLANS VIEW
008_A3.1.TIF CONSTRPLANS VIEW
009_A4.0.TIF CONSTRPLANS VIEW
010_A5.0.TIF CONSTRPLANS VIEW
011_A5.1.TIF CONSTRPLANS VIEW
012_A8.0.TIF CONSTRPLANS VIEW
013_A8.1.TIF CONSTRPLANS VIEW
014_A8.2.TIF CONSTRPLANS VIEW
015_A9.0.TIF CONSTRPLANS VIEW
016_A9.1.TIF CONSTRPLANS VIEW
017_A9.2.TIF CONSTRPLANS VIEW
018_M0.1.TIF CONSTRPLANS VIEW
019_M1.0.TIF CONSTRPLANS VIEW
020_M2.0.TIF CONSTRPLANS VIEW
021_M3.0.TIF CONSTRPLANS VIEW
022_P0.1.TIF CONSTRPLANS VIEW
023_P1.0.TIF CONSTRPLANS VIEW
024_P1.1.TIF CONSTRPLANS VIEW
025_P2.0.TIF CONSTRPLANS VIEW
026_P2.1.TIF CONSTRPLANS VIEW
027_P3.0.TIF CONSTRPLANS VIEW
028_E1.TIF CONSTRPLANS VIEW
029_E2.TIF CONSTRPLANS VIEW
030_E2.1.TIF CONSTRPLANS VIEW
031_E3.TIF CONSTRPLANS VIEW
032_E3.1.TIF CONSTRPLANS VIEW
033_E4.TIF CONSTRPLANS VIEW
034_E4.1.TIF CONSTRPLANS VIEW
035_E4.2.TIF CONSTRPLANS VIEW
036_E4.3.TIF CONSTRPLANS VIEW
037_E5.TIF CONSTRPLANS VIEW
038_K1.0.TIF CONSTRPLANS VIEW
039_K2.0.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW