Permit: T16CM05017
Permit Details
Apply Date:
06/28/2016
Applicant:
HOWELL, DAVID BARDWELL
Description:
Medical Office
Architects:
- HOWELL, DAVID BARDWELL
Permit Reviews
Permit Number - T16CM05017
Permit Status: C of o
Permit Description: Medical Office
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/02/2017 | REVISION - - 1ST | 03/02/2017 | COMPLETED |
| 06/28/2016 | PLANS OK TO SUBMIT - COMM | 06/28/2016 | COMPLETED |
| 06/28/2016 | COMMERCIAL - TI | 08/15/2016 | COMPLETED |
| 09/13/2016 | RESUBMITTAL - TI ALL | 10/13/2016 | COMPLETED |
| 11/16/2016 | RESUBMITTAL | 03/02/2017 | COMPLETED |
| 12/08/2017 | REVISION - - 2ND | 12/08/2017 | COMPLETED |
| 12/08/2017 | REVISION - - 2ND | 12/14/2017 | COMPLETED |
| 12/14/2017 | REVISION - - 2ND | 12/20/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM05017
Permit Status: C of o
Permit Description: Medical Office
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/28/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM05017
Permit Description: Medical Office
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2017 | SITE - SEWER | JMILITE1 | Approved | |
| 06/05/2017 | PLUMBING - ROUGH, SOIL | JMILITE1 | Approved | OK TO BACKFILL DWV. |
| 06/27/2017 | PLUMBING - PRE SLAB | JMILITE1 | Approved | |
| 06/27/2017 | ELECTRIC - UFER | JMILITE1 | Approved | |
| 08/04/2017 | EXT METAL CLIPS/EXT SHEATHING | JMILITE1 | Approved | |
| 08/09/2017 | ROOF NAILING | JMILITE1 | Approved | |
| 08/29/2017 | PLUMBING - MD GAS/PRECONST MTG | TVALENC1 | Approved | |
| 09/06/2017 | PLUMBING - GAS PRESSURE TEST | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/06/2017 | ELECTRIC - PROGRESS | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/12/2017 | REINFORCED MASONRY PRE-GROUT | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/12/2017 | FRAMING | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/12/2017 | BUILDING - PROGRESS | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/12/2017 | PLUMBING - ABOVE CEILING | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/12/2017 | BUILDING PRE-SLAB | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/13/2017 | PLUMBING - INTERMEDIATE | JMILITE1 | Approved | OK TO SHEET ROCK WALLS. |
| 09/18/2017 | MECHANICAL - INTERMEDIATE | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/18/2017 | ELECTRIC - INTERMEDIATE | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/29/2017 | SHEET ROCK NAILING | JMILITE1 | Approved | IVRS - Inspection :* |
| 09/29/2017 | U VALUE FOR WINDOW | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/04/2017 | STUCCO MESH | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/09/2017 | ELECTRIC - SERVICE UPGRADE | TVALENC1 | Approved | CLEAR ELECTRIC ECO |
| 10/11/2017 | TEP CLEARANCE - AM | TVALENCIA | Approved | ECO |
| 10/18/2017 | MECHANICAL - PROGRESS | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/18/2017 | PLUMBING - GAS PRESS TEST FNL | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/18/2017 | ELECTRIC - UNDERGROUND | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/23/2017 | PLUMBING - YARD WTR LINE/TEST | TVALENC1 | Approved | |
| 10/31/2017 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 10/31/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 10/31/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 11/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | IVRS - Inspection :* |
| 12/21/2017 | PLUMBING - FINAL | NORTH | Approved | PENDING WATER CHLORINATION REPORT |
| 12/21/2017 | ELECTRIC - FINAL | NORTH | Approved | |
| 12/21/2017 | FIRE - FINAL | JPEELDAVIS | Approved | |
| 12/21/2017 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
| 12/21/2017 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
| 12/27/2017 | MECHANICAL - FINAL | DQUINN | Approved | PENDING AIR BALANCE REPORT |
| 12/27/2017 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | PARTIAL C OF O OK FOR EAST SIDE OFFICES ONLY. NOT FOR SURGICAL WEST SIDE. |
| 12/27/2017 | PLUMBING - MEDICAL GAS/TEST | DQUINN | Approved | NEED GAS REPORT. |
| 12/27/2017 | BUILDING - FINAL | DQUINN | Approved | OK TO OCCUPY EAST SIDE OFFICES. NO MED GAS PRESENT. |
| 12/28/2017 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 01/05/2018 | PLUMBING - MEDICAL GAS/FINAL | TVALENC1 | Approved | IVRS - Inspection :* |