Permit: T16CM04955
Permit Details
Apply Date:
06/24/2016
Applicant:
N/A
Description:
NEW SFR
Outstanding Activity Conditions
Permit Number - T16CM04955
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/24/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T16CM04955
Permit Description: NEW SFR
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 11/25/2019 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 11/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
| 11/27/2019 | ELECTRIC - UFER | BSTEVENS | Approved | (RVI) |
| 04/07/2020 | ROOF NAILING | TVALENCIA | Approved | |
| 04/07/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 05/20/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
| 05/20/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Southwest gas clearance is required. |
| 05/20/2020 | FRAMING | ESTEVENS | Approved | |
| 05/27/2020 | RESIDENTIAL INTERMEDIATE | TVALENCIA | Approved | |
| 07/13/2020 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | approved |
| 07/24/2020 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 07/24/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | approved Clear electric ECO |
| 08/26/2020 | PLUMBING - INTERMEDIATE | JBURGE | Approved | PER 1090 |
| 08/26/2020 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | PER 1090 |
| 08/26/2020 | BUILDING - FINAL | JBURGE | Approved | Approved. Right of Way has cleared to approve Final. Please close out this permit. |
| 08/26/2020 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | Approved |
| 08/26/2020 | MECHANICAL - FINAL | JBURGE | Approved | Approved |
| 08/26/2020 | PLUMBING - FINAL | JBURGE | Approved | Approved |
| 08/26/2020 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | Approved |
| 08/26/2020 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved |
| 08/26/2020 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
| 08/26/2020 | BUILDING - FINAL | JBURGE | Approved | Partial. Pending Right of way plan revision. |