Outstanding Activity Conditions
Permit Number - T16CM03379
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/05/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T16CM03379
Permit Description: NEW SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2016 | ELECTRIC - UFER | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 07/13/2016 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 09/06/2016 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 11/04/2016 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 12/19/2016 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | ENTIRE GAS PIPE SYSTEM IS UNDER THE SLAB. THE ONLY GAS PIPE TO BE UNDER SLAB IS TO THE ISLAND STOVE. OWNER STATED THAT HE WILL REVISE PLANS. |
| 04/07/2017 | BUILDING PRE-SLAB | north | Approved | |
| 06/27/2017 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | |
| 11/20/2017 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 11/20/2017 | FRAMING | ESTEVEN1 | Approved | METAL CLIP AND TRUSSES |
| 05/09/2018 | ELECTRIC - CONSTRUCTION POWER | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | ELECTRIC - CABLE DROP | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | MECHANICAL - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | PLUMBING - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | ELECTRIC - INTERMEDIATE | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/10/2018 | TEP CLEARANCE - AM | BBENEDON | Approved | INCR |
| 10/09/2018 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
| 10/09/2018 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
| 04/02/2019 | GAS CLEARANCE | TVALENCIA | Approved | |
| 04/02/2019 | PLUMBING - FINAL | TVALENCIA | Approved | Clear gas meter |
| 04/02/2019 | PLUMBING - PROGRESS | TVALENCIA | Approved | approved upon 3090 approval from TVALENCIA |
| 07/01/2019 | ELECTRIC - FINAL | GWEST | Approved | |
| 10/30/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
| 10/30/2019 | BUILDING - FINAL | ESTEVENS | Approved |