Permit: T16CM02932
Permit Details
Apply Date:
04/21/2016
Applicant:
JOHN FENECK
Description:
DUPLEX REMODEL
Contractors:
- 2 X 2 CONSTRUCTION INC
Permit Reviews
Permit Number - T16CM02932
Permit Status: Final
Permit Description: DUPLEX REMODEL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/21/2016 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/22/2016 | COMPLETED |
05/03/2016 | RESIDENTIAL - BLDG/WWM | 06/22/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM02932
Permit Status: Final
Permit Description: DUPLEX REMODEL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/21/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T16CM02932
Permit Description: DUPLEX REMODEL
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/01/2016 | EXCAVATION/LAYOUT REBAR & ZON | Ingram | Approved | |
10/14/2016 | ROOF NAILING | BRUCE_S | Approved | |
10/14/2016 | EXT METAL CLIPS/EXT SHEATHING | BRUCE_S | Approved | |
10/14/2016 | REINFORCED MASONRY PRE-GROUT | BRUCE_S | Approved | |
11/21/2016 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
11/21/2016 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
12/02/2016 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | LEAKS NEED TO BE REPAIRED |
12/02/2016 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | |
12/02/2016 | STUCCO MESH | BSTEVENS | Approved | |
12/05/2016 | GAS CLEARANCE | BSTEVENS | Approved | |
01/10/2017 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
01/10/2017 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
01/10/2017 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
01/11/2017 | TEP CLEARANCE - AM | MPUGH | Approved | INCR |
09/21/2017 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | RESEND TEP CLEARANCE FOR UNITS 1,2,3,6,+ 7 |
09/21/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | 2" LINE - N. TO S. ON WEST SIDE, W. TO E. IN MIDDLE AND S. FROM MIDDLE RUN ON EAST SIDE OK TO BURY. |
09/21/2017 | PLUMBING - YARD WTR LINE/TEST | JMILITE1 | Approved | CANCELED BY CONTRACTOR. |
08/08/2018 | MECHANICAL - INTERMEDIATE | DFLORES2 | Approved | CLEAR SW GAS FOR BOTH UNITS |
08/08/2018 | PLUMBING - PROGRESS | DFLORES2 | Approved | CLEAR SW GAS FOR BOTH UNITS |
08/08/2018 | PLUMBING - INTERMEDIATE | DFLORES2 | Approved | CLEAR SW GAS FOR BOTH UNITS |
08/10/2018 | PLUMBING - FINAL | DQUINN | Approved | |
08/16/2018 | MECHANICAL - FINAL | MHASSAN1 | Approved | |
08/16/2018 | ELECTRIC - FINAL | MHASSAN1 | Approved | |
08/16/2018 | BUILDING - FINAL | MHASSAN1 | Approved |