Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Address NEW:
4141 E IRVINGTON RD
Apply Date:
03/10/2016
Applicant:
KENNETH LOWE
Description:
TI; FACTORY USE
Architects:
  • PAULUS, ROBERT FRANCIS
Contractors:
  • K E AND G CONSTRUCTION INC

Permit Reviews

Permit Number - T16CM01862
Permit Status: L of c
Permit Description: TI; FACTORY USE
Start Date Submittal Complete Date Status  
01/15/2019 3RD PARTY REVIEW - REVISION/OTHER 01/29/2019 COMPLETED Review Details
03/10/2016 PLANS OK TO SUBMIT - COMM 03/29/2016 COMPLETED Review Details
03/29/2016 3RD PARTY REVIEW - COMMERCIAL TI 03/29/2016 COMPLETED Review Details
03/29/2016 POST 3RD PARTY REVIEW 01/15/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T16CM01862
Permit Status: L of c
Permit Description: TI; FACTORY USE
Total Outstanding Activity Conditions - 1
Date Name
03/10/2016 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T16CM01862
Permit Description: TI; FACTORY USE
Total Completed Inspections - 27
Date Description Inspector Results Comments
10/14/2016 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/08/2020 SITE - SEWER TGUASP Approved no site sewer, this is an interior TI
12/08/2020 PLUMBING - ROOF DRAINS TGUASP Approved slopped roof with no roof drain present?
12/08/2020 PLUMBING - ROUGH, SOIL TGUASP Approved APPROVED, okay to cover.
02/03/2021 TEP CLEARANCE - PM WGALLAGHER Approved CODE INCR/4001 E IRVINGTON RD
02/09/2021 ELECTRIC - INTERMEDIATE KCOCO Approved APPROVED FOR BREAKROOM, MEN AND WOMEN BATHROOMS ONLY
03/11/2021 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved APPROVED STEM WALL FOR COLUMN
04/06/2021 FRAMING DMUNIZ Approved
04/29/2021 STUCCO MESH DMUNIZ Approved
09/08/2021 ELECTRIC - FINAL DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 OUTDOOR LIGHTING FINAL DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 MECHANICAL - INTERMEDIATE DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 EXT METAL CLIPS/EXT SHEATHING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 ROOF NAILING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 BUILDING ABOVE CEILING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 U VALUE FOR WINDOW DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 ELECTRIC - ABOVE CEILING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 PLUMBING - ABOVE CEILING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
09/08/2021 MECHANICAL - ABOVE CEILING DMUNIZ Approved Approved.



Note: provide panel labels and values at Building final.
11/08/2021 BUILDING - FINAL DMUNIZ Approved INSPECTOR APPROVED 1090. NOTES: Reference Activity T21FC00376 for following fire inspections.

5090-

9026-
11/08/2021 ENGINEERING - FINAL DMUNIZ Approved Not Applicable.
11/08/2021 ELECTRIC - OUTDOOR LIGHTING DMUNIZ Approved - Approved.
11/08/2021 MECHANICAL - FINAL DMUNIZ Approved - Approved.
11/08/2021 PLUMBING - FINAL DMUNIZ Approved - Approved.
11/08/2021 PLUMBING - PROGRESS DMUNIZ Approved - Approved.
01/18/2022 FIRE - FINAL DMUNIZ Approved T21FC00376 FINALIZED
01/18/2022 FIRE SPKLR - FINAL DMUNIZ Approved T21FC00376 FINALIZED

Documents

File Name Document Type  
LOFC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
LOFC.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
001_A0.0.TIF CONSTRPLANS VIEW
002_A1.0.TIF CONSTRPLANS VIEW
003_A2.0.TIF CONSTRPLANS VIEW
004_A3.0.TIF CONSTRPLANS VIEW
005_A4.0.TIF CONSTRPLANS VIEW
006_A5.0.TIF CONSTRPLANS VIEW
007_A6.0.TIF CONSTRPLANS VIEW
008_A6.1.TIF CONSTRPLANS VIEW
009_A6.2.TIF CONSTRPLANS VIEW
010_A7.0.TIF CONSTRPLANS VIEW
011_A7.1.TIF CONSTRPLANS VIEW
012_A7.2.TIF CONSTRPLANS VIEW
013_S1.0.TIF CONSTRPLANS VIEW
014_M1.0.TIF CONSTRPLANS VIEW
020_M1.1.TIF CONSTRPLANS VIEW
015_M2.0.TIF CONSTRPLANS VIEW
016_MP1.0.TIF CONSTRPLANS VIEW
017_P1.0.TIF CONSTRPLANS VIEW
018_P2.0.TIF CONSTRPLANS VIEW
025_P3.0.TIF CONSTRPLANS VIEW
026_P4.0.TIF CONSTRPLANS VIEW
019_E1.0.TIF CONSTRPLANS VIEW
020_E1.1.TIF CONSTRPLANS VIEW
021_E2.0.TIF CONSTRPLANS VIEW
022_E3.0.TIF CONSTRPLANS VIEW
023_S1.1.TIF CONSTRPLANS VIEW
024_S1.2.TIF CONSTRPLANS VIEW
025_S2.0.TIF CONSTRPLANS VIEW
026_S2.1.TIF CONSTRPLANS VIEW
027_S3.0.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW