Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
L of c
Type:
COMMERCIAL NEW
Apply Date:
02/17/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SHELL BUILDING
Architects:
  • DOERSCHLAG, CHRISTOPHEKURT
Contractors:
  • DOUBLE A A BUILDERS LTD ,

Permit Reviews

Permit Number - T16CM01171
Permit Status: L of c
Permit Description: NEW SHELL BUILDING
Start Date Submittal Complete Date Status  
02/17/2016 PLANS OK TO SUBMIT - COMM 02/24/2016 COMPLETED Review Details
02/24/2016 COMMERCIAL - NEW 04/06/2016 COMPLETED Review Details
04/07/2016 RESUBMITTAL 06/01/2016 COMPLETED Review Details
06/01/2016 RESUBMITTAL - TI ALL 06/07/2016 COMPLETED Review Details
06/07/2016 RESUBMITTAL 06/10/2016 COMPLETED Review Details
06/10/2016 OTHER 06/14/2016 COMPLETED Review Details
08/31/2016 REVISION - - 1ST 09/21/2016 COMPLETED Review Details
09/21/2016 REVISION - - 2ND 09/28/2016 COMPLETED Review Details
10/13/2016 REVISION - - 3RD 10/25/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T16CM01171
Permit Status: L of c
Permit Description: NEW SHELL BUILDING
Total Outstanding Activity Conditions - 1
Date Name
02/17/2016 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T16CM01171
Permit Description: NEW SHELL BUILDING
Total Completed Inspections - 30
Date Description Inspector Results Comments
07/14/2016 FIRE SPKLR - UG PIPING FLUSH CBASALDUA Approved
07/14/2016 FIRE SPKLR - UG, PIPING, HYDRO CBASALDUA Approved
07/19/2016 ELECTRIC - UFER RCAMACHO Approved RISER ONLY
07/19/2016 ELECTRIC - UFER RCAMACHO Approved IVRS - Inspection :*
10/10/2016 PLUMBING - ROOF DRAINS MRAMBER Approved IVRS - Inspection :*
11/03/2016 PLUMBING - GAS PRESSURE TEST MRAMBER Approved IVRS - Inspection :*
11/17/2016 SHEET ROCK NAILING MRAMBER Approved IVRS - Inspection :*
11/17/2016 FRAMING MRAMBER Approved IVRS - Inspection :*
11/30/2016 PLUMBING - INTERMEDIATE mramber1 Approved grease recepter ok to cover
12/15/2016 ELECTRIC - UNDERGROUND MRAMBER Approved IVRS - Inspection :*
12/15/2016 STEM WALL/RETAINING WALL MRAMBER Approved IVRS - Inspection :*
12/15/2016 REINFORCED MASONRY PRE-GROUT MRAMBER Approved IVRS - Inspection :*
12/15/2016 ELECTRIC - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
12/15/2016 BUILDING - PROGRESS MRAMBER Approved IVRS - Inspection :*
12/15/2016 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved IVRS - Inspection :*
12/15/2016 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
12/15/2016 PLUMBING - FINAL MRAMBER Approved IVRS - Inspection :*
12/15/2016 ELECTRIC - FINAL MRAMBER Approved IVRS - Inspection :*
12/20/2016 FIRE - FINAL CBASALDUA Approved
12/21/2016 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
12/21/2016 PLUMBING - YARD WTR LINE/TEST MRAMBER Approved IVRS - Inspection :*
12/21/2016 OUTDOOR LIGHTING FINAL MRAMBER Approved IVRS - Inspection :*
12/21/2016 ELECTRIC - OUTDOOR LIGHTING MRAMBER Approved IVRS - Inspection :*
12/21/2016 ELECTRIC - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
12/21/2016 U VALUE FOR WINDOW MRAMBER Approved IVRS - Inspection :*
12/21/2016 BUILDING ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
01/04/2017 BUILDING PRE-SLAB mramber1 Approved
01/04/2017 SITE - SEWER mramber1 Approved
01/04/2017 BUILDING - FINAL MRAMBER Approved IVRS - Inspection :*
01/17/2017 ENGINEERING - FINAL RLEDONNE Approved