Permit: T15EX03542
Permit Details
Apply Date:
12/18/2015
Applicant:
AMEC FOSTER WHEELER
Description:
Perform a shallow soil gas survey at twenty locations along the shoulder of roads presented in accompanying Figure. Work is projected to take 4 days total. 1 1/4" probes will temporarily be driven to 5 feet bgs for soil gas sampling (30 minutes to one hour per location). Holes will be backfilled and patched. Areas will be cleared for underground utilities.
Contractors:
- JOHNSON ENVIRONMENTAL TECHNOLOGY
Completed Inspections
Permit Status: Final
Permit Number: T15EX03542
Permit Description: Perform a shallow soil gas survey at twenty locations along the shoulder of roads presented in accompanying Figure. Work is projected to take 4 days total. 1 1/4" probes will temporarily be driven to 5 feet bgs for soil gas sampling (30 minutes to one hour per location). Holes will be backfilled and patched. Areas will be cleared for underground utilities.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2016 | TDOT-EXCAV GENERAL INSPECTION | DR | Approved | Final. No Concerns. |