Permit: T15CM08315
Permit Details
Apply Date:
11/25/2015
Applicant:
DAVID PAPANIKOLAS
Description:
ATTACHED STUDIO AND LIVING QUARTERS;RES
Permit Reviews
Permit Number - T15CM08315
Permit Status: Final
Permit Description: ATTACHED STUDIO AND LIVING QUARTERS;RES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2016 | RESUBMITTAL | 02/16/2016 | COMPLETED |
| 03/02/2016 | RESUBMITTAL | 03/02/2016 | COMPLETED |
| 10/12/2016 | REVISION - - 1ST | 10/12/2016 | COMPLETED |
| 11/25/2015 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/14/2015 | COMPLETED |
| 12/21/2016 | REVISION - - 2ND | 12/22/2016 | COMPLETED |
| 12/22/2015 | RESIDENTIAL - BLDG/WWM | 01/28/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM08315
Permit Status: Final
Permit Description: ATTACHED STUDIO AND LIVING QUARTERS;RES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/25/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T15CM08315
Permit Description: ATTACHED STUDIO AND LIVING QUARTERS;RES
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2016 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 12/01/2016 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
| 12/01/2016 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 12/09/2016 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | OK O POUR FOOTINGS |
| 12/09/2016 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 12/15/2016 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | APPROVED |
| 12/23/2016 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | OK TO TOW |
| 01/18/2017 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
| 01/24/2017 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 02/01/2017 | ROOF NAILING | BSTEVENS | Approved | |
| 02/21/2017 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 02/21/2017 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 02/21/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
| 02/21/2017 | FRAMING | JBURGE | Approved | |
| 04/21/2017 | U VALUE FOR WINDOW | NORTH | Approved | |
| 06/26/2017 | MECHANICAL - FINAL | JBURGE | Approved | |
| 06/26/2017 | PLUMBING - FINAL | JBURGE | Approved | |
| 06/26/2017 | PLUMBING - PROGRESS | JBURGE | Approved | |
| 06/26/2017 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 06/26/2017 | ELECTRIC - FINAL | JBURGE | Approved | |
| 06/26/2017 | BUILDING - FINAL | JBURGE | Approved |