Permit: T15CM06499
Permit Details
Apply Date:
09/17/2015
Applicant:
VENTURE WEST CONSTRUCTION L L C
Description:
NEW OFFICE
Architects:
- EGLIN, EVAN SAR
Contractors:
- VENTURE WEST CONSTRUCTION L L C
- VENTURE WEST INC ***APA
Permit Reviews
Permit Number - T15CM06499
Permit Status: C of o
Permit Description: NEW OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2016 | REVISION - - 1ST | 02/25/2016 | COMPLETED |
| 08/03/2016 | REVISION - - 2ND | 08/04/2016 | COMPLETED |
| 09/17/2015 | PLANS OK TO SUBMIT - COMM | 09/17/2015 | COMPLETED |
| 09/17/2015 | COMMERCIAL - NEW | 10/15/2015 | COMPLETED |
| 10/26/2015 | RESUBMITTAL - TI ALL | 11/18/2015 | COMPLETED |
| 11/24/2015 | WALK THRU - COMM | 11/25/2015 | COMPLETED |
| 12/01/2015 | WALK THRU - COMM | 12/01/2015 | COMPLETED |
| 12/02/2015 | WALK THRU - COMM | 12/02/2015 | COMPLETED |
| 12/03/2015 | OTHER | 02/24/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM06499
Permit Status: C of o
Permit Description: NEW OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/17/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM06499
Permit Description: NEW OFFICE
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2015 | PLUMBING - SEWER HCS CONNECT | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/22/2015 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/31/2015 | ELECTRIC - UNDERGROUND | BBENEDOI | Approved | IVRS - Inspection :* |
| 01/08/2016 | ELECTRIC - UFER | JMILITEL | Approved | IVRS - Inspection :* |
| 01/08/2016 | STEM WALL/RETAINING WALL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/08/2016 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
| 01/11/2016 | BUILDING PRE-SLAB | BBENEDOI | Approved | IVRS - Inspection :* |
| 02/04/2016 | ROOF NAILING | MPUGH1 | Approved | IVRS - Inspection :* |
| 02/04/2016 | EXT METAL CLIPS/EXT SHEATHING | MPUGH1 | Approved | IVRS - Inspection :* |
| 02/24/2016 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
| 03/11/2016 | MECHANICAL - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/11/2016 | PLUMBING - ABOVE CEILING | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/11/2016 | PLUMBING - YARD WTR LINE/TEST | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/11/2016 | PLUMBING - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/11/2016 | ELECTRIC - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/11/2016 | FRAMING | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/22/2016 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 03/22/2016 | STUCCO MESH | JMILITEL | Approved | IVRS - Inspection :* |
| 05/13/2016 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/13/2016 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 05/13/2016 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/22/2016 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 06/22/2016 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 06/22/2016 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 06/22/2016 | FIRE SPKLR - FINAL | nsprenger | Approved | |
| 06/23/2016 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 06/27/2016 | RIGHT OF WAY - FINAL | TAdkins | Approved | |
| 07/07/2016 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/07/2016 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/07/2016 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/07/2016 | FIRE - FINAL | nsprenger | Approved | |
| 07/07/2016 | FIRE - ALARM FINAL | nsprenger | Approved | |
| 07/08/2016 | NPPO - FINAL | RLEDONNE | Approved | |
| 07/08/2016 | SIGN - FINAL | RLEDONNE | Approved | |
| 07/08/2016 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 07/08/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 08/15/2016 | PLUMBING - BACK WATER VALVE | TVALENC1 | Approved | IVRS - Inspection :* |
| 08/18/2016 | U VALUE FOR WINDOW | jmilitello | Approved | |
| 08/18/2016 | BUILDING - FINAL | jmilitello | Approved |