Permit: T15CM06076
Permit Details
Apply Date:
08/31/2015
Applicant:
STICKLEY DESIGN GROUP
Description:
ADDITION & TI: OFFICE/OUTPATIENT SURGERY CENTER
Architects:
- STICKLEY DESIGN GROUP
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T15CM06076
Permit Status: C of o
Permit Description: ADDITION & TI: OFFICE/OUTPATIENT SURGERY CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/01/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 10/10/2016 | COMPLETED |
| 08/31/2015 | PLANS OK TO SUBMIT - COMM | 08/31/2015 | COMPLETED |
| 08/31/2015 | 3RD PARTY REVIEW - COMMERCIAL TI | 11/04/2015 | COMPLETED |
| 11/04/2015 | POST 3RD PARTY REVIEW | 11/12/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM06076
Permit Status: C of o
Permit Description: ADDITION & TI: OFFICE/OUTPATIENT SURGERY CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/31/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM06076
Permit Description: ADDITION & TI: OFFICE/OUTPATIENT SURGERY CENTER
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2015 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | IVRS - Inspection :* |
| 11/13/2015 | ELECTRIC - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 11/13/2015 | PLUMBING - MEDICAL GAS/TEST | BBENEDOI | Approved | IVRS - Inspection :* |
| 11/17/2015 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
| 11/17/2015 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
| 12/11/2015 | FRAMING | TVALENC1 | Approved | THIS INSPECTION IS FOR THE FRAMING FOR THE ADDITIONONLY |
| 12/11/2015 | ROOF NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 12/11/2015 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | IVRS - Inspection :* |
| 01/20/2016 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 03/30/2016 | ELECTRIC - SERVICE UPGRADE | MPUGH1 | Approved | IVRS - Inspection :* |
| 03/30/2016 | ELECTRIC - CABLE DROP | MPUGH1 | Approved | IVRS - Inspection :* |
| 06/08/2016 | SHEET ROCK NAILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/05/2016 | MECHANICAL - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/05/2016 | PLUMBING - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/05/2016 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/05/2016 | BUILDING ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/12/2016 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 08/22/2016 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 08/22/2016 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/23/2016 | NPPO - FINAL | MRUSSO | Approved | |
| 08/23/2016 | SIGN - FINAL | MRUSSO | Approved | |
| 08/23/2016 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 08/23/2016 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 09/22/2016 | PLUMBING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/04/2016 | PLUMBING - MD GAS/PRECONST MTG | RMORENO | Approved | |
| 10/04/2016 | MECHANICAL - INTERMEDIATE | RMORENO | Approved | |
| 10/04/2016 | PLUMBING - MEDICAL GAS/FINAL | RMORENO | Approved | |
| 10/04/2016 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | |
| 10/04/2016 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | |
| 10/04/2016 | MECHANICAL - FINAL | RMORENO | Approved | |
| 10/04/2016 | ELECTRIC - UFER | RMORENO | Approved | |
| 10/04/2016 | STUCCO MESH | RMORENO | Approved | |
| 10/04/2016 | ELECTRIC - FINAL | RMORENO | Approved | |
| 10/04/2016 | BUILDING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/04/2016 | U VALUE FOR WINDOW | RMORENO | Approved | IVRS - Inspection :* |
| 10/12/2016 | RIGHT OF WAY - FINAL | BM | Approved |