Permit: T15CM05806
Permit Details
Apply Date:
08/19/2015
Applicant:
N/A
Description:
NEW APARTMENT COMPLEX - BUILDING 4
Architects:
- EGLIN, EVAN SAR
Contractors:
- A F STERLING HOME BUILDERS LTD ,
Permit Reviews
Permit Number - T15CM05806
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX - BUILDING 4
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/11/2016 | RESUBMITTAL | 01/22/2016 | COMPLETED |
| 01/22/2016 | RESUBMITTAL | 02/10/2016 | COMPLETED |
| 02/10/2016 | RESUBMITTAL | 02/25/2016 | COMPLETED |
| 02/25/2016 | RESUBMITTAL | 03/07/2016 | COMPLETED |
| 03/07/2016 | RESUBMITTAL | 03/24/2016 | COMPLETED |
| 03/24/2016 | RESUBMITTAL | 04/28/2016 | COMPLETED |
| 04/28/2016 | REVISION - - 1ST | 05/23/2016 | COMPLETED |
| 05/23/2016 | REVISION - - 2ND | 06/15/2016 | COMPLETED |
| 06/15/2016 | REVISION - - 2ND | 06/23/2016 | COMPLETED |
| 06/23/2016 | REVISION - - 3RD | 06/30/2016 | COMPLETED |
| 06/30/2016 | REVISION - - 4TH | 07/07/2016 | COMPLETED |
| 08/02/2016 | REVISION - - 5TH | 08/08/2016 | COMPLETED |
| 08/19/2015 | PLANS OK TO SUBMIT - COMM | 08/20/2015 | COMPLETED |
| 08/26/2015 | COMMERCIAL - NEW | 10/12/2015 | COMPLETED |
| 10/12/2015 | RESUBMITTAL | 12/18/2015 | COMPLETED |
| 12/18/2015 | RESUBMITTAL | 01/11/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM05806
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX - BUILDING 4
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/19/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM05806
Permit Description: NEW APARTMENT COMPLEX - BUILDING 4
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/03/2016 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 05/27/2016 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | BUILDING #4 ONLY |
| 05/27/2016 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | BUILDING #4 ONLY |
| 06/10/2016 | FIRE SPKLR - UG PIPING FLUSH | CBASALDUA | Approved | |
| 06/24/2016 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 06/24/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 06/24/2016 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 08/09/2016 | ROOF NAILING | RCAMACHO | Approved | NAILING ONLY PROVIDE STAMPED APPROVED COT TRUSS CALCS |
| 08/09/2016 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/25/2016 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/06/2016 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDUA | Approved | |
| 10/14/2016 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | IVRS - Inspection :* |
| 10/14/2016 | ELECTRIC - TEMPORARY SERVICE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/17/2016 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
| 10/21/2016 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 10/26/2016 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/28/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/31/2016 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
| 10/31/2016 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/31/2016 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 11/07/2016 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 11/15/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 01/09/2017 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
| 01/17/2017 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | IVRS - Inspection :* |
| 03/27/2017 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 03/27/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 03/29/2017 | NPPO - FINAL | DROBERTS | Approved | |
| 03/29/2017 | SIGN - FINAL | DROBERTS | Approved | |
| 03/29/2017 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 04/06/2017 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/06/2017 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/06/2017 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/06/2017 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/06/2017 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/06/2017 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 05/11/2017 | RIGHT OF WAY - FINAL | DROBERTS | Approved | |
| 05/11/2017 | ZONING - FINAL | DROBERTS | Approved | |
| 05/11/2017 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 05/11/2017 | FIRE - FINAL | CBASALDUA | Approved |