Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T15CM05713
Permit Details
Apply Date:
08/17/2015
Applicant:
ROBIN HARTMAN
Description:
NEW SFR
Contractors:
- HARTMAN CONSTRUCTION LLC
Permit Reviews
Permit Number - T15CM05713
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/22/2017 | REVISION - - 1ST | 03/27/2017 | COMPLETED |
03/27/2017 | REVISION - - 2ND | 03/27/2017 | ACTIVE |
08/17/2015 | PLANS OK TO SUBMIT - RES | 08/17/2015 | COMPLETED |
08/17/2015 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/07/2015 | COMPLETED |
12/21/2015 | RESUBMITTAL | 02/05/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM05713
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/17/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T15CM05713
Permit Description: NEW SFR
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/06/2016 | ELECTRIC - UFER | RCAMACHO | Approved | RELOCATE TO LOWEST HORIZONTAL REBAR |
07/06/2016 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
07/25/2016 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
07/25/2016 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | IVRS - Inspection :* |
07/26/2016 | PLUMBING - SEWER HCS CONNECT | ESTEVEN1 | Approved | IVRS - Inspection :* |
08/04/2016 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | SITE WALL NORTH ONLY METAL POSTS OK TO BACK POUR |
08/18/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
11/01/2016 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
11/16/2016 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | TOP OUT FIREPACESPER DETAILS 2 & 3 / 15 ONLY |
11/22/2016 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
12/07/2016 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
12/07/2016 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | |
12/07/2016 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
12/07/2016 | STUCCO MESH | RCAMACHO | Approved | |
12/07/2016 | FRAMING | RCAMACHO | Approved | PENDING ALL TRADES |
12/16/2016 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
03/22/2017 | U VALUE FOR WINDOW | RCAMACHO | Approved | |
03/22/2017 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | OK TO CLEAR GAS |
03/23/2017 | BUILDING - PROGRESS | RCAMACHO | Approved | |
03/23/2017 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | |
03/23/2017 | ELECTRIC - FINAL | RCAMACHO | Approved | |
03/23/2017 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | |
03/23/2017 | MECHANICAL - FINAL | RCAMACHO | Approved | |
03/23/2017 | GAS CLEARANCE | RCAMACHO | Approved | |
03/28/2017 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
03/28/2017 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
03/28/2017 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |