Permit: T15CM05651
Permit Details
Apply Date:
08/13/2015
Applicant:
MATT CONLEY
Description:
SOLAR PV R1: CHANGE OUT UNDERGROUND CONDUIT SIZE
Contractors:
- TECHNICIANS FOR SUSTAINABILITY L L C *C
Permit Reviews
Permit Number - T15CM05651
Permit Status: Final
Permit Description: SOLAR PV
R1: CHANGE OUT UNDERGROUND CONDUIT SIZE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/13/2015 | PLANS OK TO SUBMIT - RES | 08/13/2015 | COMPLETED |
| 08/13/2015 | RESIDENTIAL - BLDG/WWM | 08/21/2015 | COMPLETED |
| 09/02/2015 | REVISION - WALK THRU | 09/02/2015 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T15CM05651
Permit Status: Final
Permit Description: SOLAR PV
R1: CHANGE OUT UNDERGROUND CONDUIT SIZE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/13/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T15CM05651
Permit Description: SOLAR PV
R1: CHANGE OUT UNDERGROUND CONDUIT SIZE
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2015 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | UNDERGROUND CONDUIT APPROVED. OKAY TO BACKFILL TRENCH |
| 09/02/2015 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/02/2015 | ELECTRIC - UNDERGROUND | IVR USER | Approved | IVRS - RI canceled |
| 09/14/2015 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/14/2015 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 09/14/2015 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/15/2015 | TEP CLEARANCE - AM | mramber | Approved | DGC |