Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
08/06/2015
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
WATER TREATMENT PLANT
Architects:
  • MICKELBERG, PAUL DAVID
Contractors:
  • DURAZO CONSTRUCTION CORPORATION

Permit Reviews

Permit Number - T15CM05405
Permit Status: C of o
Permit Description: WATER TREATMENT PLANT
Start Date Submittal Complete Date Status  
01/08/2016 OTHER 01/15/2016 COMPLETED Review Details
01/27/2016 3RD PARTY REVIEW - REVISION/OTHER-2ND 03/24/2016 COMPLETED Review Details
04/21/2016 REVISION - - 1ST 04/29/2016 COMPLETED Review Details
08/06/2015 PLANS OK TO SUBMIT - COMM 08/14/2015 COMPLETED Review Details
08/18/2015 3RD PARTY REVIEW - COMMERCIAL 09/23/2015 COMPLETED Review Details
09/09/2016 3RD PARTY REVIEW - REVISION/OTHER 09/14/2016 COMPLETED Review Details
09/23/2015 POST 3RD PARTY REVIEW 10/05/2015 COMPLETED Review Details
10/06/2015 POST 3RD PARTY REVIEW 01/08/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T15CM05405
Permit Status: C of o
Permit Description: WATER TREATMENT PLANT
Total Outstanding Activity Conditions - 1
Date Name
08/06/2015 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T15CM05405
Permit Description: WATER TREATMENT PLANT
Total Completed Inspections - 40
Date Description Inspector Results Comments
03/14/2016 ELECTRIC - UFER AQUIROZ Approved IVRS - Inspection :*
04/15/2016 SITE - SEWER AQUIROZ Approved
06/24/2016 EXT METAL CLIPS/EXT SHEATHING AQUIROZ Approved
07/20/2016 MECHANICAL - INTERMEDIATE AQUIROZ Approved
07/20/2016 PLUMBING - INTERMEDIATE AQUIROZ Approved
07/20/2016 ELECTRIC - INTERMEDIATE AQUIROZ Approved
07/20/2016 FRAMING AQUIROZ Approved
07/20/2016 ROOF NAILING AQUIROZ Approved
08/30/2016 BUILDING ABOVE CEILING AQUIROZ Approved
08/30/2016 U VALUE FOR WINDOW AQUIROZ Approved
08/30/2016 ELECTRIC - ABOVE CEILING AQUIROZ Approved
08/30/2016 PLUMBING - ABOVE CEILING AQUIROZ Approved
08/30/2016 MECHANICAL - ABOVE CEILING AQUIROZ Approved
09/01/2016 FIRE SPKLR - UG PIPING FLUSH CBASALDUA Approved
09/08/2016 FIRE SPKLR - UG, PIPING, HYDRO jvincent Approved We did not visualize UG. Per Harvey we are accepting the contractors test certificate for the UG.
09/08/2016 FIRE SPKLR - OH PIPING & HYDRO jvincent Approved wet side approved by CB
dry side by JV
09/09/2016 NPPO - FINAL RLEDONNE Approved
09/09/2016 SIGN - FINAL RLEDONNE Approved
09/09/2016 LANDSCAPE - FINAL RLEDONNE Approved
09/09/2016 RIGHT OF WAY - FINAL tadkins Approved No RWY work
09/12/2016 ELECTRIC - SERVICE UPGRADE AQUIROZ Approved
09/12/2016 PLUMBING - GAS PRESSURE TEST AQUIROZ Approved
09/12/2016 PLUMBING - FINAL AQUIROZ Approved
09/12/2016 PLUMBING - SEWER HCS CONNECT AQUIROZ Approved
09/12/2016 PLUMBING - YARD WTR LINE/TEST AQUIROZ Approved
09/12/2016 PLUMBING - ROUGH, SOIL AQUIROZ Approved
09/12/2016 OUTDOOR LIGHTING FINAL AQUIROZ Approved
09/12/2016 ELECTRIC - OUTDOOR LIGHTING AQUIROZ Approved
09/12/2016 ELECTRIC - CABLE DROP AQUIROZ Approved
09/12/2016 ELECTRIC - UNDERGROUND AQUIROZ Approved
09/12/2016 SHEET ROCK NAILING AQUIROZ Approved
09/12/2016 BUILDING PRE-SLAB AQUIROZ Approved
09/12/2016 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved
09/13/2016 FIRE - ALARM FINAL CBASALDUA Approved
09/13/2016 FIRE SPKLR - FINAL CBASALDUA Approved
09/13/2016 FIRE - FINAL CBASALDUA Approved
09/14/2016 MECHANICAL - FINAL AQUIROZ Approved
09/14/2016 ELECTRIC - FINAL AQUIROZ Approved
11/29/2016 BUILDING - FINAL DROBERTS Approved
11/29/2016 ENGINEERING - FINAL DROBERTS Approved