Apply Date:
07/30/2015
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW RETAIL GROCERY
Architects:
- GROOMS, DAVID BARTON
Contractors:
- CORSTONE CONTRACTORS LLC
Permit Reviews
Permit Number - T15CM05249
Permit Status: C of o
Permit Description: NEW RETAIL GROCERY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/30/2015 | PLANS OK TO SUBMIT - COMM | 07/30/2015 | COMPLETED |
| 07/30/2015 | COMMERCIAL - NEW | 09/10/2015 | COMPLETED |
| 09/10/2015 | RESUBMITTAL | 11/02/2015 | COMPLETED |
| 11/02/2015 | RESUBMITTAL | 02/10/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM05249
Permit Status: C of o
Permit Description: NEW RETAIL GROCERY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/30/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM05249
Permit Description: NEW RETAIL GROCERY
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2016 | PLUMBING - ROUGH, SOIL | bbenedo | Approved | |
| 03/21/2016 | BUILDING PRE-SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 04/25/2016 | ELECTRIC - OUTDOOR LIGHTING | BBENEDON | Approved | IVRS - Inspection :* |
| 04/25/2016 | ROOF NAILING | BBENEDON | Approved | IVRS - Inspection :* |
| 04/25/2016 | EXT METAL CLIPS/EXT SHEATHING | BBENEDON | Approved | IVRS - Inspection :* |
| 05/05/2016 | FIRE SPKLR - OH PIPING & HYDRO | nsprenger | Approved | |
| 05/05/2016 | FIRE SPKLR - UG PIPING FLUSH | nsprenger | Approved | |
| 05/05/2016 | FIRE SPKLR - UG, PIPING, HYDRO | nsprenger | Approved | |
| 05/09/2016 | STUCCO MESH | BBENEDON | Approved | IVRS - Inspection :* |
| 05/10/2016 | REINFORCED MASONRY PRE-GROUT | BBENEDON | Approved | IVRS - Inspection :* |
| 05/18/2016 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2016 | BUILDING ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2016 | MECHANICAL - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2016 | MECHANICAL - HOODS | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2016 | FRAMING | BBENEDON | Approved | IVRS - Inspection :* |
| 06/28/2016 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 07/05/2016 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 07/06/2016 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | ELECTRIC - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | ELECTRIC - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | ELECTRIC - UFER | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | U VALUE FOR WINDOW | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | STEM WALL/RETAINING WALL | BBENEDON | Approved | IVRS - Inspection :* |
| 07/06/2016 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDON | Approved | IVRS - Inspection :* |
| 07/20/2016 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/21/2016 | MECHANICAL - FINAL | TVALENC1 | Approved | IVRS - Inspection :* 1- TYPE 1 GREASE EXHAUST HOOD FINAL IS OKAY. NOTE: SHALL PROVIDE A CAPTION AND CONTAINMENT VERFICATION TE4ST BY OTHER TO BE SUBMITTED AT THE TIME OF THE BLDG. FINAL. |
| 07/21/2016 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
| 07/21/2016 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 07/21/2016 | RIGHT OF WAY - FINAL | MBravin | Approved | Per Mike Bravin site inspection performed by Donny Russell. No issues. |
| 07/21/2016 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 07/21/2016 | FIRE SPKLR - FINAL | CBASALDUA | Approved | 1. Need to complete sprinkler punch list on subcontractor permit. |
| 07/21/2016 | NPPO - FINAL | RLEDONNE | Approved | |
| 07/21/2016 | SIGN - FINAL | RLEDONNE | Approved | |
| 07/22/2016 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/25/2016 | FIRE - FINAL | nsprenger | Approved | |
| 07/26/2016 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
| 07/26/2016 | SITE - SEWER | TVALENCIA | Approved | |
| 07/26/2016 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 07/26/2016 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 07/26/2016 | PLUMBING - ABOVE CEILING | TVALENCIA | Approved | |
| 07/26/2016 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | |
| 07/26/2016 | ELECTRIC - TEMPORARY SERVICE | TVALENCIA | Approved | |
| 07/26/2016 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 07/26/2016 | BUILDING - PROGRESS | TVALENCIA | Approved | |
| 07/26/2016 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 07/26/2016 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 07/27/2016 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 07/27/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 08/05/2016 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved |