Permit: T15CM04285
Permit Details
Apply Date:
06/24/2015
Applicant:
N/A
Description:
HACIENDA AT THE RIVER; BLDG- 4 ASSIST LIVING TCO APPROVED TO STOCK WITH FURNITURE AND APPLY FOR LICENSING
Contractors:
- WEITZ COMPANY L L C *C
Permit Reviews
Permit Number - T15CM04285
Permit Status: C of o
Permit Description: HACIENDA AT THE RIVER; BLDG- 4 ASSIST LIVING TCO APPROVED TO STOCK WITH FURNITURE AND APPLY FOR LICENSING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/29/2016 | REVISION - - 2ND | 03/29/2016 | COMPLETED |
| 03/29/2016 | REVISION - - 2ND | 04/12/2016 | COMPLETED |
| 06/17/2015 | REVISION - - 1ST | 08/06/2015 | COMPLETED |
| 08/07/2015 | REVISION - - 1ST | 11/20/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM04285
Permit Status: C of o
Permit Description: HACIENDA AT THE RIVER; BLDG- 4 ASSIST LIVING TCO APPROVED TO STOCK WITH FURNITURE AND APPLY FOR LICENSING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/24/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM04285
Permit Description: HACIENDA AT THE RIVER; BLDG- 4 ASSIST LIVING TCO APPROVED TO STOCK WITH FURNITURE AND APPLY FOR LICENSING
Total Completed Inspections - 50
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/31/2015 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 03/29/2016 | ELECTRIC - UFER | BSTEVENS | Approved | IVRS - Inspection :* |
| 03/29/2016 | BUILDING PRE-SLAB | BSTEVENS | Approved | IVRS - Inspection :* |
| 03/29/2016 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | IVRS - Inspection :* |
| 03/29/2016 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 04/15/2016 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 06/06/2016 | ROOF NAILING | BSTEVENS | Approved | |
| 07/12/2016 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 07/20/2016 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 07/20/2016 | BUILDING - PROGRESS | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 07/20/2016 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 07/20/2016 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 07/20/2016 | PLUMBING - ROOF DRAINS | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 07/20/2016 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 07/20/2016 | MECHANICAL - ABOVE CEILING | BSTEVENS | Approved | ABOVE CEILING ALL OK TO COVER. GAS PRESSURE TEST OK. ROOF DRAIN TEST OK. WATER LINE TEST OK. |
| 08/16/2016 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | IVRS - Inspection :* OK TO COVER PVC PORTION. CONNECTION TO COPPER RISER NOT DONE YET. |
| 09/01/2016 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
| 09/01/2016 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 09/01/2016 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 09/02/2016 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | OK TO DRYWALL ONE SIDE ONLY |
| 09/07/2016 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
| 09/07/2016 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | INTERIOR WALLS AT TOP PLATES OK. OK TO CLOSE WALLS. |
| 09/07/2016 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | INTERIOR WALLS AT TOP PLATES OK. OK TO CLOSE WALLS. |
| 09/07/2016 | FRAMING | BSTEVENS | Approved | INTERIOR WALLS AT TOP PLATES OK. OK TO CLOSE WALLS. |
| 09/09/2016 | STUCCO MESH | BRUCE.S | Approved | CAULK ALL PENETRATIONS THROUGH FOAM BOARD. |
| 09/14/2016 | MECHANICAL - INTERMEDIATE | BRUCE_S | Approved | |
| 10/26/2016 | MECHANICAL - HOODS | BSTEVENS | Approved | FINAL SMOKE TEST OK |
| 01/06/2017 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | |
| 01/06/2017 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 01/06/2017 | PLUMBING - PROGRESS | BSTEVENS | Approved | |
| 01/12/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 01/12/2017 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 01/12/2017 | SITE - SEWER | BSTEVENS | Approved | |
| 01/12/2017 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 01/12/2017 | MECHANICAL - FINAL | BSTEVENS | Approved | |
| 01/13/2017 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
| 01/17/2017 | FIRE SPKLR - FINAL | jvincent | Approved | previously approved |
| 01/17/2017 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | previously approved |
| 01/17/2017 | FIRE SPKLR - UG PIPING FLUSH | jvincent | Approved | previously approved |
| 01/17/2017 | FIRE SPKLR - UG, PIPING, HYDRO | jvincent | Approved | previously approved |
| 01/30/2017 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | PARKING LOT LIGHTS ALL OK. |
| 01/30/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | RECN |
| 01/31/2017 | RIGHT OF WAY - FINAL | DR | Approved | |
| 01/31/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 01/31/2017 | NPPO - FINAL | MRUSSO | Approved | |
| 01/31/2017 | SIGN - FINAL | MRUSSO | Approved | |
| 01/31/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 01/31/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 02/01/2017 | BUILDING - FINAL | CTREVYLIAN | Approved | |
| 02/01/2017 | FIRE - ALARM FINAL | jvincent | Approved | approved by CB 01/30/17. |