Permit: T15CM03375
Permit Details
Apply Date:
05/20/2015
Applicant:
PAGE, ROBERT ELWOOD
Description:
NEW GUEST HOUSE SFR
Architects:
- PAGE, ROBERT ELWOOD
Contractors:
- JON JOHNSON DESIGN & CONSTRUCTION
Permit Reviews
Permit Number - T15CM03375
Permit Status: Final
Permit Description: NEW GUEST HOUSE SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2016 | REVISION - - 1ST | 05/23/2016 | COMPLETED |
| 05/20/2015 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 08/19/2015 | COMPLETED |
| 08/19/2015 | RESIDENTIAL - BLDG/WWM | 10/06/2015 | COMPLETED |
| 10/15/2015 | RESUBMITTAL | 11/16/2015 | COMPLETED |
| 11/16/2015 | RESUBMITTAL | 03/21/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM03375
Permit Status: Final
Permit Description: NEW GUEST HOUSE SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/20/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T15CM03375
Permit Description: NEW GUEST HOUSE SFR
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/11/2016 | ELECTRIC - UFER | MPUGH1 | Approved | IVRS - Inspection :* |
| 04/11/2016 | BUILDING PRE-SLAB | MPUGH1 | Approved | IVRS - Inspection :* |
| 04/11/2016 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH1 | Approved | IVRS - Inspection :* |
| 05/20/2016 | PLUMBING - SEWER HCS CONNECT | INGRAM | Approved | |
| 05/20/2016 | ELECTRIC - UNDERGROUND | INGRAM | Approved | 2ND STRUCTURE TO MAIN |
| 05/20/2016 | PLUMBING - ROUGH, SOIL | INGRAM | Approved | ACCESSORY STRUCTURE TO STREET |
| 05/20/2016 | PLUMBING - GAS PRESSURE TEST | INGRAM | Approved | |
| 06/02/2016 | ELECTRIC - SERVICE UPGRADE | INGRAM | Approved | |
| 06/27/2016 | ROOF NAILING | Ingram | Approved | |
| 07/14/2016 | REINFORCED MASONRY PRE-GROUT | Ingram | Approved | |
| 07/14/2016 | MECHANICAL - INTERMEDIATE | Ingram | Approved | |
| 07/14/2016 | PLUMBING - INTERMEDIATE | Ingram | Approved | |
| 07/14/2016 | ELECTRIC - INTERMEDIATE | Ingram | Approved | |
| 07/14/2016 | FRAMING | Ingram | Approved | |
| 09/14/2016 | U VALUE FOR WINDOW | Ingram | Approved | |
| 10/30/2016 | MECHANICAL - FINAL | JBURGE | Approved | |
| 10/30/2016 | PLUMBING - FINAL | JBURGE | Approved | |
| 10/30/2016 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 10/30/2016 | ELECTRIC - FINAL | JBURGE | Approved | |
| 10/30/2016 | BUILDING - FINAL | JBURGE | Approved | |
| 10/30/2016 | STUCCO MESH | JBURGE | Approved | |
| 10/31/2016 | GAS CLEARANCE | JBURGE | Approved |