Permit: T15CM01891
Permit Details
Apply Date:
03/20/2015
Applicant:
ANDREW OGAS
Description:
ADD 2 BEDROOMS/ 2 BATHS - T15DV01828
Architects:
- ANDREW OGAS
Contractors:
- DESERT COURTYARD HOMES
Permit Reviews
Permit Number - T15CM01891
Permit Status: Final
Permit Description: ADD 2 BEDROOMS/ 2 BATHS - T15DV01828
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/20/2015 | PLANS OK TO SUBMIT - RES | 03/20/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM01891
Permit Status: Final
Permit Description: ADD 2 BEDROOMS/ 2 BATHS - T15DV01828
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/20/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T15CM01891
Permit Description: ADD 2 BEDROOMS/ 2 BATHS - T15DV01828
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2015 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/02/2015 | ELECTRIC - UFER | DQUINN | Approved | |
| 04/02/2015 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 04/02/2015 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 04/10/2015 | ROOF NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/13/2015 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 04/13/2015 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
| 04/16/2015 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
| 04/16/2015 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/16/2015 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 04/16/2015 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/17/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 04/17/2015 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 07/15/2015 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | PLUMBING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | OUTDOOR LIGHTING FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | ELECTRIC - SERVICE UPGRADE | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/15/2015 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |