Permit: T15CM01051
Permit Details
Apply Date:
02/17/2015
Applicant:
RICHMOND AMERICAN CONSTRUCTION INC
Description:
SFR RICHT30S13 T13-M0008
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T15CM01051
Permit Status: C of o
Permit Description: SFR RICHT30S13 T13-M0008
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/17/2015 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 02/17/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM01051
Permit Status: C of o
Permit Description: SFR RICHT30S13 T13-M0008
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/17/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM01051
Permit Description: SFR RICHT30S13 T13-M0008
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/02/2015 | PLUMBING - SEWER HCS CONNECT | WLAHR | Approved | IVRS - Inspection :* |
03/02/2015 | PLUMBING - YARD WTR LINE/TEST | WLAHR | Approved | IVRS - Inspection :* |
03/02/2015 | PLUMBING - ROUGH, SOIL | WLAHR | Approved | IVRS - Inspection :* |
03/05/2015 | BUILDING PRE-SLAB | WLAHR | Approved | IVRS - Inspection :* |
03/05/2015 | EXCAVATION/LAYOUT REBAR & ZON | WLAHR | Approved | IVRS - Inspection :* |
03/20/2015 | ROOF NAILING | JBURGE | Approved | OK TO DRY-IN |
03/20/2015 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
03/20/2015 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
04/07/2015 | PLUMBING - GAS PRESSURE TEST | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | ELECTRIC - TEMPORARY SERVICE | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | ELECTRIC - CABLE DROP | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | ELECTRIC - INTERMEDIATE | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | ELECTRIC - UFER | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | U VALUE FOR WINDOW | WLAHR | Approved | IVRS - Inspection :* |
04/07/2015 | STUCCO MESH | WLAHR | Approved | IVRS - Inspection :* |
04/08/2015 | TEP CLEARANCE - AM | WLAHR | Approved | ECO |
04/09/2015 | FRAMING | WLAHR | Approved | IVRS - Inspection :* |
04/09/2015 | MECHANICAL - INTERMEDIATE | WLAHR | Approved | IVRS - Inspection :* |
04/09/2015 | PLUMBING - INTERMEDIATE | WLAHR | Approved | IVRS - Inspection :* |
04/20/2015 | SHEET ROCK NAILING | WLAHR | Approved | IVRS - Inspection :* |
05/20/2015 | PLUMBING - GAS PRESS TEST FNL | MPUGH | Approved | IVRS - Inspection :* |
05/21/2015 | GAS CLEARANCE | MPUGH | Approved | |
05/26/2015 | PLUMBING - FINAL | RCANCINO | Approved | |
05/26/2015 | OUTDOOR LIGHTING FINAL | RCANCINO | Approved | |
05/26/2015 | ELECTRIC - FINAL | RCANCINO | Approved | |
05/27/2015 | MECHANICAL - FINAL | RCANCINO | Approved | |
05/27/2015 | BUILDING - FINAL | RCANCINO | Approved |